02 Feb 2024

14:34 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
Support to start using WMS the system for handy terminal & pegasus system Arunwit Isarapongporn
14:34 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
Support to start using WMS the system for handy terminal & pegasus system Arunwit Isarapongporn
14:34 8.00 hours (Project progress work #94 (Closed): [On-site support]Support after cutover)
Support to start using WMS the system for handy terminal & pegasus system Arunwit Isarapongporn

31 Jan 2024

16:41 4.00 hours (Project progress work #51 (Closed): Overall project development for web and handy)
Improve the BOM, Stock maintenance report and stock inquiry report Kittisak Isarapongporn
 