From 28 Nov 2023 to 07 Dec 2023

07 Dec 2023

14:07 8.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Teaching about WMS and handy Arunwit Isarapongporn
14:06 8.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Teaching about WMS and handy Arunwit Isarapongporn
00:57 7.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Final teaching Kittisak Isarapongporn
14:06 8.00 hours (Project progress work #266 (Closed): Make manual document for Pegasus)
Make manual document for Pegasus Arunwit Isarapongporn
01:02 4.00 hours (Project progress work #51 (Closed): Overall project development for web and handy)
Create NG Report page and store procedure Kittisak Isarapongporn

01 Dec 2023

23:44 8.00 hours (Project progress work #52 (Closed): Issue topics)
Modify getStockFifo and convertItemUnitQty Kittisak Isarapongporn

29 Nov 2023

16:54 8.00 hours (Project progress work #266 (Closed): Make manual document for Pegasus)
Arunwit Isarapongporn

28 Nov 2023

12:45 8.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
UAT about the WMS system and onsite support Arunwit Isarapongporn
01:40 4.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Test and teach to users Kittisak Isarapongporn
12:45 8.00 hours (Project progress work #266 (Closed): Make manual document for Pegasus)
Arunwit Isarapongporn
01:32 4.00 hours (Project progress work #52 (Closed): Issue topics)
Create the NG report that it is able to create the schedules to compensate for the NG. Kittisak Isarapongporn
 