Activity
From 20 Nov 2023 to 29 Nov 2023
29 Nov 2023
28 Nov 2023
- 12:45 8.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
- UAT about the WMS system and onsite support
- 01:40 4.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
- Test and teach to users
- 12:45 8.00 hours (Project progress work #266 (Closed): Make manual document for Pegasus)
- 01:32 4.00 hours (Project progress work #52 (Closed): Issue topics)
- Create the NG report that it is able to create the schedules to compensate for the NG.
24 Nov 2023
21 Nov 2023
- 17:20 4.00 hours (Project progress work #52 (Closed): Issue topics)
- Integrate and test the BT print function
- 17:15 5.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
- UAT and teaching