09 Nov 2023
07 Nov 2023
- 10:40 Project progress work #204 (In Progress): UAT about the WMS system and onsite support
- 10:39 Project progress work #204 (Closed): UAT about the WMS system and onsite support
05 Nov 2023
- 17:24 Project progress work #183 (Closed): Modify the item master to add the picture preview
- 17:24 Project progress work #182 (Closed): UAT about the WMS system
- 17:24 Project progress work #53 (Closed): UAT about the WMS system
03 Nov 2023
- 17:49 Project progress work #183 (Close request): Modify the item master to add the picture preview
- 17:46 Project progress work #183 (Closed): Modify the item master to add the picture preview
- 17:45 Project progress work #182 (Close request): UAT about the WMS system
- 17:44 Project progress work #182 (Closed): UAT about the WMS system
- 17:41 Project progress work #53 (Close request): UAT about the WMS system
- 17:40 Project progress work #163 (In Progress): Import BOM/Modify script to manage uncontrol items and outsource details
- 15:40 Sales support #83 (In Progress): PJ - line monitoring assembly & PJ- Machine operation monitoring Molding line
- 15:35 Project progress work #170 (Closed): Add the item picture preview
- 15:32 Project progress work #162 (Closed): Found BT connection failed to Sato WS4 label printer