21:40 10.00 hours (Project progress work #142 (Closed): UAT about the WMS system and onsite support)
Ryo Nozaki

20 Oct 2023

17:12 8.00 hours (Project progress work #51 (Closed): Overall project development for web and handy)
Modify the web and DB schema to mapping the item to supplier ID and add the uncontrol flag for all items. Create the ... Kittisak Isarapongporn
 