Parent project #3042: [PJ250093] CKD Management System Monitoring Tools for Windows Server
Project progress work #3149: [Requirement definition]
Project progress work #3150: [Internal Design]
Project progress work #3152: [Installation&On-site support]
Project progress work #637: [Development] Modify dashboard
Parent project #1022: [PJ250028] IKD Management System for A.N.I.
Project progress work #3101: [Coding] Web Development
Project progress work #3138: [Coding] Trouble Report
Project progress work #3135: [Coding] Reprint Case mark document
Project progress work #3148: [Installation&On-site support]
Project progress work #3054: [Coding] Handy UI Script
Project progress work #3072: [Coding] WS api and frontend script fixing
Project progress work #3142: [Installation&Onsite support]
Project progress work #3141: [Installation&On-site support]
Parent project #1058: [PJ250037] CKD system Phase 06
Project progress work #1066: [Coding] Handy development
Project progress work #1067: [Installation&On-site support]
Project progress work #3366: [Installation&On-site support] Supports user feedback
Project progress work #3372: [Installation&On-site support] Teaching for Go live
Project progress work #3376: [Installation&On-site support] Go live
Project progress work #3373: [Installation&On-site support] Pre-Go live for 1line
Project progress work #3374: [Installation&Onsite support] On-line program modification
Project progress work #3375: [Installation&Onsite support] Monitoring program install
Project progress work #3365: [Installation&On-site support] User Testing & Trial (WC)
Project progress work #3364: [Installation&On-site support] SD card installation 8units
Project progress work #1064: [Requirement definition]

Status

In Progress
New
New
New
New
New
In Progress
New
New
New
New
In Progress
New
New
New
In Progress
In Progress
New
New
New
New
New
New
New
New
New
New
In Progress

Priority

Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal

Total estimated time

0.00
16.00
3158.00
830.00
32.00
8.00
136.00
520.00
32.00
1744.00
240.00
1336.00
120.00
80.00
8.00
8.00
24.00
40.00
8.00
120.00
8.00

Total spent time

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Updated

09 Dec 2025 08:52
09 Dec 2025 08:52
09 Dec 2025 08:53
09 Dec 2025 08:53
09 Dec 2025 08:54
12 Jun 2024 16:27
11 Mar 2026 14:51
12 Dec 2025 16:59
04 Dec 2025 17:04
04 Dec 2025 17:02
23 Dec 2025 10:02
12 Dec 2025 16:57
11 Mar 2026 14:55
23 Dec 2025 10:01
11 Mar 2026 14:51
05 Mar 2026 15:56
24 Feb 2026 16:16
18 Mar 2026 15:26
23 Dec 2025 15:59
23 Dec 2025 16:04
23 Dec 2025 16:17
23 Dec 2025 16:05
23 Dec 2025 16:06
23 Dec 2025 16:07
23 Dec 2025 14:27
23 Dec 2025 14:19
11 Mar 2026 11:38
05 Mar 2026 15:56
 
 
45
46
47
48
49
50
51
52
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Tomas Tech All Project Management
 
 
A.N.I. LOGISTICS, LTD.
New 0%
 
 
 
 
In Progress
Parent project #1022: [PJ250028] IKD Management System for A.N.I.

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Oct 2024
Due date: 06 Mar 2026
Assignee: Kittisak Isarapongporn
Priority: Normal
 
 
 
 
New 98%
Project progress work #3101: [Coding] Web Development

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 26 Jun 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
 
 
 
New 80%
Project progress work #3138: [Coding] Trouble Report

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 02 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
 
 
New 0%
Project progress work #3135: [Coding] Reprint Case mark document

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 04 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
 
 
 
New 60%
Project progress work #3148: [Installation&On-site support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 10 Sep 2025
Due date: 26 Dec 2025
Assignee: Kittisak Isarapongporn
Priority: Normal
 
 
 
 
In Progress 100%
Project progress work #3054: [Coding] Handy UI Script

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Oct 2025
Due date: 02 Dec 2025
Assignee: Tanong Amnuaypornsri
Priority: Normal
 
 
 
 
New 100%
Project progress work #3072: [Coding] WS api and frontend script fixing

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 01 Oct 2025
Due date: 23 Feb 2026
Assignee:
Priority: Normal
 
 
 
New 60%
Project progress work #3142: [Installation&Onsite support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 10 Nov 2025
Due date: 27 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
 
 
 
 
 
New 100%
Project progress work #3141: [Installation&On-site support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Mar 2026
Due date: 06 Mar 2026
Assignee: Tanong Amnuaypornsri
Priority: Normal
 
 
 
 
In Progress
Parent project #1058: [PJ250037] CKD system Phase 06

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 11 Aug 2025
Due date: 01 Mar 2026
Assignee: Kittisak Isarapongporn
Priority: Normal
 
 
 
 
In Progress 100%
Project progress work #1066: [Coding] Handy development

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 15 Sep 2025
Due date: 18 Feb 2026
Assignee: Priroj Neamjarn
Priority: Normal
 
 
 
 
 
New 88%
Project progress work #1067: [Installation&On-site support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 01 Mar 2026
Assignee:
Priority: Normal
 
 
 
New 80%
Project progress work #3366: [Installation&On-site support] Supports user feedback

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 23 Nov 2025
Assignee:
Priority: Normal
 
 
 
New 90%
Project progress work #3372: [Installation&On-site support] Teaching for Go live

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 16 Nov 2025
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #3376: [Installation&On-site support] Go live

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Nov 2025
Due date: 17 Nov 2025
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #3373: [Installation&On-site support] Pre-Go live for 1line

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Dec 2025
Due date: 17 Dec 2025
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #3374: [Installation&Onsite support] On-line program modification

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Dec 2025
Due date: 19 Dec 2025
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #3375: [Installation&Onsite support] Monitoring program install

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Dec 2025
Due date: 19 Dec 2025
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #3365: [Installation&On-site support] User Testing & Trial (WC)

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 22 Dec 2025
Due date: 26 Dec 2025
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #3364: [Installation&On-site support] SD card installation 8units

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 25 Dec 2025
Due date: 25 Dec 2025
Assignee:
Priority: Normal
 
 
 
 
 
New 100%
Project progress work #6690: [Issue]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 18 Jan 2026
Due date: 01 Mar 2026
Assignee:
Priority: Normal
 
 
 
 
 
In Progress 100%
Project progress work #1064: [Requirement definition]

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Mar 2026
Due date: 01 Mar 2026
Assignee: Kittisak Isarapongporn
Priority: Normal
 

Also available in: PDF PNG