27 Dec 2025
- 09:32 Project progress work #2967 (Closed): [Installation&On-site support] Panel
- 09:32 Project progress work #2966 (Closed): [Installation&On-site support] Trim
26 Dec 2025
- 18:36 Project progress work #3349 (Confirmation request): [Installation&On-site support] UAT/Fix Issue/Go live
- today
-UAT Test Weight scale process
24 Dec 2025
- 17:28 Project progress work #3349: [Installation&On-site support] UAT/Fix Issue/Go live
- today
-UAT Test Weight scale process
tomorrow
-UAT Test Weight scale process
23 Dec 2025
- 16:56 Project progress work #3349: [Installation&On-site support] UAT/Fix Issue/Go live
- today
-fix issue weight scale process
tomorrow
-Install update apk on site - 16:29 Project progress work #3371 (Closed): [Installation&On-site support] Modification: Inner packing & Q-Gate take photo(PANEL)
- 16:04 Project progress work #3371 (Closed): [Installation&On-site support] Modification: Inner packing & Q-Gate take photo(PANEL)
- 16:29 Project progress work #3369 (Closed): [Installation&On-site support] Modification: Inner packing multiple device scan add issue (PANEL)
- 16:01 Project progress work #3369 (Closed): [Installation&On-site support] Modification: Inner packing multiple device scan add issue (PANEL)
- 16:29 Project progress work #3370 (Closed): [Installation&On-site support]
- 16:02 Project progress work #3370 (Closed): [Installation&On-site support]
- 16:28 Project progress work #3368 (Closed): [Installation&On-site sdupport] Modification: Inner packing multiple device scan(PANEL)
- 16:00 Project progress work #3368 (Closed): [Installation&On-site sdupport] Modification: Inner packing multiple device scan(PANEL)
- 16:28 Project progress work #3356 (Closed): [Installation&On-site support] Weight scale installation & wiring
- 14:14 Project progress work #3356 (Closed): [Installation&On-site support] Weight scale installation & wiring
- 16:28 Project progress work #3357 (Closed): [Installation&On-site support] Weight scale installation 2 units
- 14:15 Project progress work #3357 (Closed): [Installation&On-site support] Weight scale installation 2 units
- 16:28 Project progress work #3367 (Closed): [Installation&Onsite support] Modification: Switch table
- 16:00 Project progress work #3367 (Closed): [Installation&Onsite support] Modification: Switch table
- 16:17 Project progress work #3376 (New): [Installation&On-site support] Go live
- 16:07 Project progress work #3375 (New): [Installation&Onsite support] Monitoring program install
- 16:06 Project progress work #3374 (New): [Installation&Onsite support] On-line program modification
- 16:05 Project progress work #3373 (New): [Installation&On-site support] Pre-Go live for 1line
- 16:04 Project progress work #3372 (New): [Installation&On-site support] Teaching for Go live
- 15:59 Project progress work #3366 (New): [Installation&On-site support] Supports user feedback
- 14:27 Project progress work #3365 (New): [Installation&On-site support] User Testing & Trial (WC)
- 14:21 Project progress work #3363 (Closed): [Installation&On-site support] SD card installation 7units testing
- 14:18 Project progress work #3363 (Closed): [Installation&On-site support] SD card installation 7units testing
- 14:21 Project progress work #2991 (Closed): [Installation&On-site support] UAT of weight scale (1 Set)
- 14:07 Project progress work #2991 (In Progress): [Installation&On-site support] UAT of weight scale (1 Set)
- 13:44 Project progress work #2991 (Closed): [Installation&On-site support] UAT of weight scale (1 Set)
- 14:20 Project progress work #2975 (Closed): [Installation&On-site support] Import master weight data
- 14:04 Project progress work #2975 (In Progress): [Installation&On-site support] Import master weight data
- 13:35 Project progress work #2975 (Closed): [Installation&On-site support] Import master weight data
- 14:20 Project progress work #2967 (In Progress): [Installation&On-site support] Panel
- 14:20 Project progress work #2967 (Close request): [Installation&On-site support] Panel
- 14:20 Project progress work #2983 (Closed): [Installation&On-site support] UAT of weight scale (9 Set)
- 14:06 Project progress work #2983 (In Progress): [Installation&On-site support] UAT of weight scale (9 Set)
- 13:38 Project progress work #2983 (Closed): [Installation&On-site support] UAT of weight scale (9 Set)
- 14:19 Project progress work #3362 (Closed): [Installation&On-site support] SD card installation 7units
- 14:18 Project progress work #3362 (Closed): [Installation&On-site support] SD card installation 7units
- 14:19 Project progress work #3360 (Closed): [Installation&On-site support] Weight scale installation 7 units
- 14:17 Project progress work #3360 (Closed): [Installation&On-site support] Weight scale installation 7 units
- 14:19 Project progress work #3364 (New): [Installation&On-site support] SD card installation 8units
- 14:17 Project progress work #3361 (New): [Installation&On-site support] Weight scale config&testing 7 units
- 14:16 Project progress work #3359 (New): [Installation&On-site support] Weight scale config&testing 2 units
- 14:15 Project progress work #3358 (New): [Installation&On-site support] Weight scale config&testing 2 units
- 14:13 Project progress work #3355 (New): [Installation&On-site support] User Testing & Trial
- 14:13 Project progress work #3354 (New): [Installation&On-site support] Teaching for UT
- 13:44 Project progress work #2990 (Closed): Installation&On-site support] Install Hardware weight scale (1 Set)
- 13:44 Project progress work #2989 (Closed): [Installation&On-site support] Modify Label Tag Receive (Test)
- 13:44 Project progress work #2988 (Closed): [Installation&On-site support] Training User
- 13:44 Project progress work #2987 (Closed): [Installation&On-site support] Import master Ocr-Qpoint check
- 13:44 Project progress work #2986 (Closed): [Installation&On-site support] Handy Set IP and Install APK 22 devices
- 13:39 Project progress work #2985 (Closed): [Installation&On-site support] Create Table Master
- 13:38 Project progress work #2984 (Closed): [Installation&On-site support] Install WebSocket controller Panel
- 13:38 Project progress work #2982 (Closed): [Installation&On-site support] Install Hardware weight scale (9 Set)
- 13:37 Project progress work #2981 (Closed): [Installation&On-site support] UAT of weight scale (1 Set)
- 13:37 Project progress work #2980 (Closed): [Installation&On-site support] Install Hardware weight scale (1 Set)
- 13:37 Project progress work #2978 (Closed): [Installation&On-site support] Internal Test IV/IM
- 13:37 Project progress work #2979 (Closed): [Installation&On-site support] Modify Label Tag Receive (Test)
- 13:37 Project progress work #1066 (Closed): [Coding] Handy development
- 13:37 Project progress work #2977 (Closed): [Installation&On-site support] Modify web socket
- 13:37 Project progress work #2976 (Closed): [Installation&On-site support] Training User
- 13:35 Project progress work #2974 (Closed): [Installation&On-site support] Import master program IM data / UAT IM Process
- 13:34 Project progress work #2973 (Closed): [Installation&On-site support] Import master program IV data / UAT IV Process
- 13:34 Project progress work #2972 (Closed): [Installation&On-site support] UAT Inner packing Process PC with Handy
- 13:34 Project progress work #2971 (Closed): [Installation&On-site support] Import master Ocr-Qpoint check
- 13:34 Project progress work #2970 (Closed): [Installation&On-site support] Handy Set IP and Install APK 41 devices
22 Dec 2025
- 18:02 Project progress work #3349: [Installation&On-site support] UAT/Fix Issue/Go live
- today
UAT Test Weight Scale on site
tomorrow
Fix issue - 16:10 Project progress work #3349 (In Progress): [Installation&On-site support] UAT/Fix Issue/Go live
- 16:10 Project progress work #3349 (Confirmation request): [Installation&On-site support] UAT/Fix Issue/Go live
- 16:10 Project progress work #2969 (Closed): [Installation&On-site support] Create Table Master
- 16:10 Project progress work #2968 (Closed): [Installation&On-site support] Install WebSocket controller Trim