04 Nov 2025
- 17:50 Project progress work #1486: [Coding] WS (Weight Scale-Big part) - Outer Packing
- today
-Create UI and Socket for Weight scale big parts process
tomorrow
-Install and training - 16:16 Parent project #907 (Closed): [PJ250012] Production Management System
- 16:16 Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project
03 Nov 2025
- 18:28 Project progress work #1485: [Coding] WS (Weight Scale-Small/Medium part) - Outer Packing
- today
-Create UI and Socket for Weight scale small medium parts process
tomorrow
-Create UI and Socket for Weight ...
31 Oct 2025
- 17:03 Project progress work #1485: [Coding] WS (Weight Scale-Small/Medium part) - Outer Packing
- today
-Create UI and Socket for Weight scale small medium parts process
tomorrow
-Create UI and Socket for Weight ...
30 Oct 2025
- 17:04 Project progress work #1485: [Coding] WS (Weight Scale-Small/Medium part) - Outer Packing
- today
-Create UI and Socket for Weight scale small medium parts process
tomorrow
-Create UI and Socket for Weight ... - 09:21 Project progress work #1482 (Closed): [Coding] ANI, Web Socket Q-Point Inner packing
- 09:21 Project progress work #1481 (Closed): [Coding] ANI,OCR Handy QGate Check
- 09:20 Project progress work #1483 (Closed): [Coding] OCR - IV
- 09:20 Project progress work #1484 (Closed): [Coding] OCR - IM
- 09:19 Project progress work #1486 (In Progress): [Coding] WS (Weight Scale-Big part) - Outer Packing
- 09:18 Project progress work #1065 (Closed): [Internal Design]
- 09:17 Project progress work #1065 (In Progress): [Internal Design]
- 09:18 Project progress work #1075 (Closed): Electrical Diagram Weight Checker
- 09:17 Project progress work #1480 (Closed): [Coding] ANI,OCR Handy PANEL INNER PACKING
- 09:15 Parent project #708 (Closed): IKD System - Migrate AS400 to Pegasus at PCB site
- 09:14 Parent project #712 (Closed): EKD System phase4 for ANI Ayuthaya
- 09:14 Project progress work #892 (Closed): [Development] Enhance the web function and ui
- 09:14 Project progress work #801 (Closed): EKD system phase 4
- 09:13 Parent project #585 (Closed): [PJ240002]Digital picking system for ANI for Cloud usage fee 2024
- 09:12 Parent project #570 (Closed): [PJ230056]Handyterminal app for A.N.I.
- 09:08 Parent project #531 (Closed): [PJ220022]Tablet system phase2
- 09:07 Parent project #530 (Closed): [PJ230054] CKD process management system phase3 for ANI