22 Sep 2025

17:32 8.00 hours (Project progress work #1066 (In Progress): [Coding] Handy development)
Create Process check q-point check inner packing (UI) Priroj Neamjarn
17:32 8.00 hours (Project progress work #1066 (In Progress): [Coding] Handy development)
Create Process check q-point check inner packing (UI) Priroj Neamjarn

20 Sep 2025

00:34 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:26 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:24 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:23 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:23 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:16 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:14 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:13 5.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:10 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:07 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:06 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
00:28 2.00 hours (Parent project #1059 (Closed): [PJ250038] CKD system add Camera system & handy temrinal OCR function Hardware)
Kittisak Isarapongporn
00:21 2.00 hours (Parent project #1059 (Closed): [PJ250038] CKD system add Camera system & handy temrinal OCR function Hardware)
Kittisak Isarapongporn
00:18 4.00 hours (Parent project #1059 (Closed): [PJ250038] CKD system add Camera system & handy temrinal OCR function Hardware)
Kittisak Isarapongporn
00:01 8.00 hours (Parent project #1059 (Closed): [PJ250038] CKD system add Camera system & handy temrinal OCR function Hardware)
Kittisak Isarapongporn

19 Sep 2025

23:57 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:53 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:53 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:52 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:51 8.00 hours (Parent project #1059 (Closed): [PJ250038] CKD system add Camera system & handy temrinal OCR function Hardware)
Kittisak Isarapongporn

17 Sep 2025

17:57 8.00 hours (Project progress work #1066 (In Progress): [Coding] Handy development)
-Create Process check q-point check inner packing (UI) Priroj Neamjarn
17:57 8.00 hours (Project progress work #1066 (In Progress): [Coding] Handy development)
-Create Process check q-point check inner packing (UI) Priroj Neamjarn

16 Sep 2025

17:46 8.00 hours (Project progress work #1066 (In Progress): [Coding] Handy development)
Create new menu phase 6 Priroj Neamjarn

14 Sep 2025

15:51 8.00 hours (Project progress work #1313 (Closed): [Coding] DB SP/Trigger)