20 Jan 2025

18:56 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Adjust Setup/Vanning Process,QGate Process Priroj Neamjarn
18:56 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
Adjust Setup/Vanning Process,QGate Process Priroj Neamjarn

19 Jan 2025

08:56 8.00 hours (Project progress work #892 (Closed): [Development] Enhance the web function and ui)
Adjust label layout and check printer issue today Kittisak Isarapongporn
08:52 8.00 hours (Project progress work #892 (Closed): [Development] Enhance the web function and ui)
Improve import function and create manual check label generate Kittisak Isarapongporn

18 Jan 2025

16:44 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
-Adjust Setup/Vanning Process Priroj Neamjarn
16:44 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
-Adjust Setup/Vanning Process Priroj Neamjarn

17 Jan 2025

18:54 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
install the application Priroj Neamjarn
18:54 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
install the application Priroj Neamjarn

16 Jan 2025

16:44 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
install the application. Priroj Neamjarn
16:44 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
install the application. Priroj Neamjarn
 