26 Nov 2024
- 16:39 Project progress work #739: [Development] CKD process system phase4
- today
PC Schedule Outer, Schedule Vanning
Q-Point detail report
tomorrow
Packing daily summary report
Packing mo... - 14:01 Project progress work #131 (Confirmation request): [Coding]Android handy and tablet modification Java
25 Nov 2024
- 16:18 Project progress work #739: [Development] CKD process system phase4
- today
-PC Schedule Receive, Schedule Staging, Schedule Inner
PC Schedule Outer, Schedule Vanning
tomorrow
-PC Sch...
22 Nov 2024
- 16:32 Project progress work #739: [Development] CKD process system phase4
- today
-PC Schedule Receive, Schedule Staging, Schedule Inner
tomorrow
-PC Schedule Outer, Schedule Vanning
21 Nov 2024
- 16:50 Project progress work #739: [Development] CKD process system phase4
- today
-Edit Tag Receive label
-PC Schedule Receive, Schedule Staging
tomorrow
-PC Schedule Receive, Schedule Staging
20 Nov 2024
- 16:31 Project progress work #739: [Development] CKD process system phase4
- today
-Vanning Finish Case (Tablet)
-Edit Tag Receive label
tomorrow
-PC Schedule Receive, Schedule Staging
19 Nov 2024
- 16:19 Project progress work #739: [Development] CKD process system phase4
- today
-Vanning Finish Case (Handy)
-Vanning Finish Case (Tablet)
tomorrow
-Edit Tag Receive label
-PC Schedule R...
18 Nov 2024
- 16:35 Project progress work #739: [Development] CKD process system phase4
- today
-Setup Finish Case (Handy)
-Setup Finish Case (Tablet)
tomorrow
-Vanning Finish Case (Handy)
-Vanning Fini...