16:34 Project progress work #739: [Development] CKD process system phase4
today
-Move Finish Case (Handy)
-Setup Finish Case (Handy)
tomorrow
-Setup Finish Case (Handy)
-Setup Finish Cas...
Priroj Neamjarn

12 Nov 2024

16:43 Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case (Tablet)
-Move Finish Case (Handy)
tomorrow
-Move Finish Case (Handy)
Priroj Neamjarn

11 Nov 2024

16:32 Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case (Handy)
tomorrow
-Receive Finish Case (Tablet)
-Move Finish Case (Handy)
Priroj Neamjarn

08 Nov 2024

16:37 Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case
tomorrow
-Receive Finish Case
Priroj Neamjarn

07 Nov 2024

16:46 Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case
-Lock screen
tomorrow
-Receive Finish Case
Priroj Neamjarn

06 Nov 2024

16:35 Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case
tomorrow
-Lock screen
-Receive Finish Case
Priroj Neamjarn

05 Nov 2024

16:31 Project progress work #739: [Development] CKD process system phase4
today
-Outer Packing Process
tomorrow
-Lock screen
-Receive Finish Case
Priroj Neamjarn

04 Nov 2024

16:36 Project progress work #739: [Development] CKD process system phase4
today
-Outer Packing Process
tomorrow
-Outer Packing Process
-Lock screen
-Receive Finish Case
Priroj Neamjarn
 

Also available in: Atom