28 Oct 2024

16:38 Project progress work #739: [Development] CKD process system phase4
today
-New Main menu (phase 4)
-Inner Packing Process (new customer request)
-Multi scan handy
tomorrow
-Outer P...
Priroj Neamjarn

25 Oct 2024

16:35 Project progress work #739: [Development] CKD process system phase4
today
-New Main menu (phase 4)
-Outer Packing Process
-Inner Packing Process (new customer request)
Priroj Neamjarn

22 Oct 2024

16:44 Project progress work #739: [Development] CKD process system phase4
today
-Login process
tomorrow
-Outer Packing Process
-Inner Packing Process (new customer request)
Priroj Neamjarn

21 Oct 2024

16:32 Project progress work #739: [Development] CKD process system phase4
today
-Inner Packing process
-Login process
tomorrow
-Login process
-Outer Packing Process
Priroj Neamjarn
08:26 Project progress work #739: [Development] CKD process system phase4
today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process
Priroj Neamjarn
 