11 Sep 2024
- 13:45 4.00 hours (Project progress work #131 (Closed): [Coding]Android handy and tablet modification Java)
06 Sep 2024
- 16:35 1.00 hour (Project progress work #713 (Closed): [Documentation] CKD Phase4 - Get requirements of project)
- Kickoff meeting at online
04 Sep 2024
- 20:27 8.00 hours (Parent project #708 (Closed): IKD System - Migrate AS400 to Pegasus at PCB site)
- Meeting at on-site
02 Sep 2024
- 17:27 2.00 hours (Project progress work #130 (Closed): [Coding]Inner packing screen function C#)
- Check and fix the incorrect data from racing condition problem on OUTER PACKING STEP3 of Handy
- 00:44 2.00 hours (Project progress work #130 (Closed): [Coding]Inner packing screen function C#)
- Support and check the problem from user