14 Nov 2023

16:58 Project progress work #226 (In Progress): CKD project requirement and document preparation
Kittisak Isarapongporn
16:57 Project progress work #226 (Closed): CKD project requirement and document preparation
Kittisak Isarapongporn
13:26 Project progress work #225 (In Progress): CCTV Installation
[ To day ]
- Contact supplier CCTV shadjan To bring CCTV equipment to test on 30/11/23 at 1:00 PM at A.N.I.
Equipme...
Nattapol Poeam
13:16 Project progress work #225 (Closed): CCTV Installation
CCTV Installation Nattapol Poeam

11 Nov 2023

17:50 Problem-Bug #221 (Close request): Found the problem with the handy show "Schedule not found"
Kittisak Isarapongporn

10 Nov 2023

16:53 Problem-Bug #221 (Confirmation request): Found the problem with the handy show "Schedule not found"
Kittisak Isarapongporn
16:52 Problem-Bug #221 (Closed): Found the problem with the handy show "Schedule not found"
Problem:
The handy always shows the "Schedule not found".
Causes:
The label has the missing data in QRCode.
S...
Kittisak Isarapongporn
16:47 Problem-Bug #151 (Interruption): Changed request: HATC's date format will be changed on this November
Kittisak Isarapongporn

08 Nov 2023

22:51 Problem-Bug #214 (In Progress): Found the problem with the handy being able to scan the other label [STAGING AREA]
Read and check the sequence number with the master plan on the handheld scan.
1. Modify the handheld in staging scan...
Kittisak Isarapongporn
22:40 Problem-Bug #214 (Closed): Found the problem with the handy being able to scan the other label [STAGING AREA]
Problem:
Found the problem with the handy being able to scan the other label which same as the designated part but w...
Kittisak Isarapongporn
21:42 Sales support #179 (Close request): Join the meeting at on-site
Kittisak Isarapongporn
21:42 Sales support #179 (Confirmation request): Join the meeting at on-site