Project

General

Profile

Actions

Parent project #5397

closed

[PJ260010] Infrastructure IoT system for NTN Manufacturing(Thailand) Hardware PT

Added by Siriwilai Chaiwattanaphon 5 months ago. Updated 30 days ago.

Status:
Closed
Priority:
Normal
Start date:
02 Feb 2026
Due date:
22 Mar 2026

Description

1. Electrical cost
1.1 Electrical part 1 set
2. Electrical labore cost
2.1 Inside: Drawing design 1 job
2.2 Outside: Installation and Wiring 1 job
2.3 Outside: Power on and Test 1 job
2.4 Out-Site: Packing and Transportation 1 job
3. Software
3.1 Specification design 1 job
3.2 Program design and Development 1 job
4. Installation
4.1 Program Installation and I/O Check 1 job
4.2 Program test 1 job
4.3 Program Commissioning 1 job
4.4 Electrical Installation 1 job


Subtasks 22 (0 open22 closed)

Project progress work #5398: [Requirement Definition]Closed02 Feb 202608 Feb 2026

Actions
Project progress work #6457: [Requirement definition] Kick-off meetingClosedKonlawat Saechee03 Feb 202603 Feb 2026

Actions
Project progress work #6458: [Requirement definition] Requirements confirmationClosedKonlawat Saechee02 Feb 202608 Feb 2026

Actions
Project progress work #5399: [Internal Design]Closed02 Feb 202615 Feb 2026

Actions
Project progress work #6459: [Internal Design] System DesignClosedKonlawat Saechee02 Feb 202615 Feb 2026

Actions
Project progress work #5400: [Coding]Closed09 Feb 202624 Feb 2026

Actions
Project progress work #6460: [Coding] Hardware procurementClosedKonlawat Saechee09 Feb 202620 Feb 2026

Actions
Project progress work #6461: [Coding] Hardware pre-shipment confirmationClosedKonlawat Saechee16 Feb 202620 Feb 2026

Actions
Project progress work #6856: [Coding] Modification software for support addition powermeter.ClosedSuphawat Tinaso19 Feb 202624 Feb 2026

Actions
Project progress work #5401: [Installation&On-site support]Closed21 Feb 202622 Mar 2026

Actions
Project progress work #6462: [Installation&On-site support] Power Meter installationClosedKonlawat Saechee21 Feb 202624 Feb 2026

Actions
Project progress work #6463: [Installation&On-site support] Software installation (PLC)ClosedKonlawat Saechee25 Feb 202626 Feb 2026

Actions
Project progress work #6464: [Installation&On-site support] Software installation (Application)ClosedKonlawat Saechee26 Feb 202627 Feb 2026

Actions
Project progress work #6465: [Installation&On-site support] Software installation (Web Application)ClosedKonlawat Saechee26 Feb 202627 Feb 2026

Actions
Project progress work #6466: [Installation&On-site support] Teaching for UTClosedKonlawat Saechee27 Feb 202627 Feb 2026

Actions
Project progress work #6467: [Installation&On-site support] User Testing & TrialClosedKonlawat Saechee28 Feb 202608 Mar 2026

Actions
Project progress work #6468: [Inatallation&On-site support] Supports user feedbackClosedKonlawat Saechee28 Feb 202608 Mar 2026

Actions
Project progress work #6469: [Installation&On-site support] Teaching for Go liveClosedKonlawat Saechee28 Feb 202608 Mar 2026

Actions
Project progress work #6470: [Inatallation&On-site support] Go liveClosedKonlawat Saechee09 Mar 202622 Mar 2026

Actions
Project progress work #6767: [Installation&On-site support] InstallationClosedTaweesak Suriyon21 Feb 202623 Feb 2026

Actions
Project progress work #6857: [Installation&On-site support] install software and validationClosedSuphawat Tinaso27 Feb 202602 Mar 2026

Actions
Project progress work #7061: [Installation&On-site support] UATClosedSuphawat Tinaso03 Mar 202610 Mar 2026

Actions
Actions