closed

[PJ260006] Camera system Preventive maintenance for STV

Added by Siriwilai Chaiwattanaphon 5 months ago. Updated 9 days ago.

Status:
Closed
Priority:
Normal
Start date:
13 Jan 2026
Due date:
09 May 2026

Description

Installation
Software configuration & Adjustment 1 Day
Transportation expenses 1 person day 1 time


Files


Subtasks 10 (0 open10 closed)

Project progress work #4459: [Requirement Definition]ClosedPhatthadon Inthachot13 Jan 202614 Jan 2026

Actions
Project progress work #4460: [Internal Design]ClosedPhatthadon Inthachot23 Jan 202631 Jan 2026

Actions
Project progress work #6794: [Internal design] Preventive Maintenance SD 2 stationClosedPhatthadon Inthachot28 Jan 202631 Jan 2026

Actions
Project progress work #6795: [Internal design] QT Support PM SD 2 day [Request done] (waiting QT)ClosedPhatthadon Inthachot23 Jan 202627 Jan 2026

Actions
Project progress work #4461: [Coding] ClosedPhatthadon Inthachot30 Jan 202630 Jan 2026

Actions
Project progress work #6563: [Coding] Onsite add alarm function.ClosedSermsak Prowee30 Jan 202630 Jan 2026

Actions
Project progress work #4462: [Installation&On-site support] ClosedPhatthadon Inthachot29 Jan 202609 May 2026

Actions
Project progress work #4463: [Installation&On-site support] Preventive maintenanceClosedPhatthadon Inthachot29 Jan 202630 Jan 2026

Actions
Project progress work #4464: [Installation&On-site support] Report preventive maintenance summaryClosedPhatthadon Inthachot02 Feb 202606 Feb 2026

Actions
Project progress work #8263: [Installation&On-site support] Onsite fix PLC function.ClosedSermsak Prowee09 May 202609 May 2026

Actions
Actions #1

Updated by Waraporn Promsopa 9 days ago

  • Status changed from In Progress to Closed
Actions