23:10 ADVICS MANUFACTURING (THAILAND) CO., LTD. Sales support #164: IoT system for CNC line follow up
- Estimate cost
- Estimate time
* I'm not sure about data extraction from CNC machines.
Nattapol Poeam
16:00 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. Project progress work #230 (In Progress): MC30OP80 program modification and create document for k.Boonyarit
Nattapol Poeam
11:57 TOMAS TECH CO., LTD. Project progress work #233 (In Progress): Edit the data transmission concept of the Demo-Box line notify alert job.
Nattapol Poeam
11:54 TOMAS TECH CO., LTD. Project progress work #233 (Closed): Edit the data transmission concept of the Demo-Box line notify alert job.
- Change the concept of data transmission between PC and PLC. Previously using FTP File CSV method to PC caused a pro... Nattapol Poeam
11:39 TOMAS TECH CO., LTD. Project progress work #165 (In Progress): IoT demo kit prepare box for Metarex at Nov
Nattapol Poeam

15 Nov 2023

15:53 NISSAN MOTOR (THAILAND) CO., LTD. Sales support #216 (Confirmation request): NMT1&2,Trim Chassis shop To install OCR system project
Wait PO Nattapol Poeam
15:51 ADVICS MANUFACTURING (THAILAND) CO., LTD. Sales support #217 (In Progress): Meeting about Loss analysis system IoT project ( New Project )
[ Topic of today's meeting ] In-charge person K.Tanapiwat ( K.Got ),K.Noom <> Production ABS Section
>>> The custome...
Nattapol Poeam
15:01 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. Project progress work #218 (Confirmation request): Wiring lan cable and power cable of LineMC30 OP80
Nattapol Poeam

14 Nov 2023

13:28 THAI NIPPON FOODS CO., LTD. Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project.
List equipment of TNF_PJ230043
https://drive.google.com/drive/folders/1RhnGOBfTuZGQImPFWH4omgd_8RDj5-Ir?usp=drive_li...
Nattapol Poeam
13:26 A.N.I. LOGISTICS, LTD. Project progress work #225 (In Progress): CCTV Installation
[ To day ]
- Contact supplier CCTV shadjan To bring CCTV equipment to test on 30/11/23 at 1:00 PM at A.N.I.
Equipme...
Nattapol Poeam
13:16 A.N.I. LOGISTICS, LTD. Project progress work #225 (Closed): CCTV Installation
CCTV Installation Nattapol Poeam

13 Nov 2023

17:11 THAI NIPPON FOODS CO., LTD. Sales support #175: EV charger installation project
Next action
> Support customer
> Wait PO
Nattapol Poeam
17:00 TOMAS TECH CO., LTD. Project progress work #223 (In Progress): Internal check stock
Nattapol Poeam
16:59 TOMAS TECH CO., LTD. Project progress work #223 (Closed): Internal check stock
Check stock equipment all project Nattapol Poeam
16:54 KEYENCE (THAILAND) CO., LTD. Sales support #219 (Confirmation request): Keyence meeting
Purpose
- To update technics function and application
- To summarize onhand projects
- Update function PLC KV8000
...
Nattapol Poeam

10 Nov 2023

16:52 THAI NIPPON FOODS CO., LTD. Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project.
Summarize equipment before order and requst a quotation supplier Nattapol Poeam
15:30 PANASONIC AUTOMOTIVE SYSTEMS ASIA PACIFIC CO.,LTD. Sales support #67: Automatic label pasting machine Concept proposal
[ Today ]
Meeting agenda
1. Packet material
2. Layout machine
3. Process flow
[ Requiment from customer ]
1. Mo...
Nattapol Poeam
15:04 MITSUBISHI HEAVY INDUSTRIES-MAHAJAK AIR CONDITIONERS CO., LTD. Project progress work #211: MACO monitor robot in production line IoT project
Update estimate cost MACO Nattapol Poeam

09 Nov 2023

19:04 MITSUBISHI HEAVY INDUSTRIES-MAHAJAK AIR CONDITIONERS CO., LTD. Project progress work #211: MACO monitor robot in production line IoT project
Wait price from Keyence Nattapol Poeam
08:39 MITSUBISHI HEAVY INDUSTRIES-MAHAJAK AIR CONDITIONERS CO., LTD. Project progress work #211: MACO monitor robot in production line IoT project
[ To day ]
Meeting topic ( Request )
- Concept line production 14 Machine.
- Can monitor the operation of machines...
Nattapol Poeam
17:12 THAI NIPPON FOODS CO., LTD. Project progress work #220 (In Progress): Design drawing and confirm equipment
Nattapol Poeam
17:09 THAI NIPPON FOODS CO., LTD. Project progress work #220 (Closed): Design drawing and confirm equipment
Design drawing
- TB Box
- I/O
Nattapol Poeam
15:58 KEYENCE (THAILAND) CO., LTD. Sales support #219 (Closed): Keyence meeting
[ Purpose of the meeting ]
- To update technics function and application.
- To summarize onhand projects.
Nattapol Poeam
15:55 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. Project progress work #218 (Closed): Wiring lan cable and power cable of LineMC30 OP80
[ Task ]
- Wiring lan cable and power cable of LineMC30 OP80
- Config parameter SR2000
- Test trigger and monitor ...
Nattapol Poeam
15:50 ADVICS MANUFACTURING (THAILAND) CO., LTD. Sales support #217 (Closed): Meeting about Loss analysis system IoT project ( New Project )
In charge K.Tanapiwat [ Tel 086-156-8060 ]
Name production : Control
Onsite meeting Date 14/11/23 Time 10:00
Nattapol Poeam
10:57 NISSAN MOTOR (THAILAND) CO., LTD. Sales support #216 (In Progress): NMT1&2,Trim Chassis shop To install OCR system project
Nattapol Poeam
10:56 NISSAN MOTOR (THAILAND) CO., LTD. Sales support #216 (Closed): NMT1&2,Trim Chassis shop To install OCR system project
[ Meeting topic ]
- A summary of the entire work scope of the project will be given to each maker who comes to the m...
Nattapol Poeam
09:39 ATA CASTING TECHNOLOGY CO., LTD. Problem-Bug #215 (In Progress): Request verification of the data collection of machine
Nattapol Poeam
09:34 ATA CASTING TECHNOLOGY CO., LTD. Problem-Bug #215 (Closed): Request verification of the data collection of machine
The customer requested that the machine be inspected for traceability regarding recording data of the Laser mark and ... Nattapol Poeam

07 Nov 2023

22:38 MITSUBISHI HEAVY INDUSTRIES-MAHAJAK AIR CONDITIONERS CO., LTD. Project progress work #211 (In Progress): MACO monitor robot in production line IoT project
Nattapol Poeam
22:38 MITSUBISHI HEAVY INDUSTRIES-MAHAJAK AIR CONDITIONERS CO., LTD. Project progress work #211 (Closed): MACO monitor robot in production line IoT project
In-Charge K.Anawill
On-site meeting
Nattapol Poeam
22:25 PANDORA PRODUCTION CO., LTD. Sales support #210 (In Progress): Auto trigger read QR-Code for Pandora project
Nattapol Poeam
22:25 PANDORA PRODUCTION CO., LTD. Sales support #210 (Closed): Auto trigger read QR-Code for Pandora project
Install and config SRX-300 for Read QR-Code from part customer Nattapol Poeam
22:18 BIG STAR CO., LTD. Sales support #209 (In Progress): Shoe size sorting machine project Concept proposal
Nattapol Poeam
22:17 BIG STAR CO., LTD. Sales support #209 (Closed): Shoe size sorting machine project Concept proposal
Build a conveyor belt system for sorting shoes and sorting shoe sizes for BIG Star Co.,Ltd project Nattapol Poeam
22:05 TAKEBE (THAILAND) CO., LTD. Sales support #208 (In Progress): Takebe meeting about IoT monitoring system Project
Nattapol Poeam
22:03 TAKEBE (THAILAND) CO., LTD. Sales support #208 (Closed): Takebe meeting about IoT monitoring system Project
People involved
Meji : Khun Kritsana chuay-rod ( Phone 080-942-9242 )
CKD : Khun Narongchai watcharenwong ( 084-694...
Nattapol Poeam
21:48 PANASONIC AUTOMOTIVE SYSTEMS ASIA PACIFIC CO.,LTD. Sales support #207 (Confirmation request): Meeting about review 3D Design
Nattapol Poeam
21:47 PANASONIC AUTOMOTIVE SYSTEMS ASIA PACIFIC CO.,LTD. Sales support #207 (Closed): Meeting about review 3D Design
Meeting about review 3D Design
- Conveyor design
- Tool robot design
- Sequence design
- Overall system
Nattapol Poeam
16:18 TOMAS TECH CO., LTD. Sales support #202 (Confirmation request): Meeting with the Keyence team about the new project Demo-kit.
The customer requested a case study on the Demo-Kit to present to supervisors involved in the decision to create the ... Nattapol Poeam
09:58 TOMAS TECH CO., LTD. Sales support #202 (In Progress): Meeting with the Keyence team about the new project Demo-kit.
Nattapol Poeam
16:17 THAI NIPPON FOODS CO., LTD. Project progress work #201 (In Progress): Summary of all equipment for use in the Machine operation monitoring systems project.
Nattapol Poeam
16:13 THAI NIPPON FOODS CO., LTD. Project progress work #201 (Confirmation request): Summary of all equipment for use in the Machine operation monitoring systems project.
Nattapol Poeam
 