Arunwit Isarapongporn's activity

From 03 Nov 2023 to 12 Nov 2023

09 Nov 2023

21:45 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #197 (Closed): Support installation HT-Label printing system Phase 2)
Install Server and config application&DB on Server, Config printer IP address&Setting printer name Arunwit Isarapongporn
21:45 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #197 (Closed): Support installation HT-Label printing system Phase 2)
Install Server and config application&DB on Server, Config printer IP address&Setting printer name Arunwit Isarapongporn

07 Nov 2023

15:42 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #95: Support installation for power supply and LAN cable for 20 points
[07/11/2023]
- Install the power plug LAN cable connection point and Access point installation point
- Make electri...
Arunwit Isarapongporn
15:42 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Arunwit Isarapongporn
15:40 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Sales support #178 (Closed): Support to start using the system for Label printing system)
Update setting config of printer label 17 point and test print label all complete Arunwit Isarapongporn
15:38 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Sales support #178 (Closed): Support to start using the system for Label printing system)
Update setting config of printer label 27 point and test print label complete. The remaining 17 will be set up and t... Arunwit Isarapongporn

04 Nov 2023

14:25 TOMAS TECH CO., LTD. 8.00 hours (Sales support #48 (Closed): Redmine email notifications)
Redmine email notifications setting Arunwit Isarapongporn
14:24 TOMAS TECH CO., LTD. 8.00 hours (Sales support #48 (Closed): Redmine email notifications)
Redmine email notifications setting Arunwit Isarapongporn
09:19 TOMAS TECH CO., LTD. Sales support #48 (Confirmation request): Redmine email notifications
[04/11/2023]
Redmine email notifications is already complete.
Arunwit Isarapongporn
09:19 TOMAS TECH CO., LTD. 1.00 hour (Sales support #48 (Closed): Redmine email notifications)
Arunwit Isarapongporn
14:18 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Sales support #178 (Closed): Support to start using the system for Label printing system)
Support to start using the system for Label printing system Arunwit Isarapongporn
14:17 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Sales support #178 (Closed): Support to start using the system for Label printing system)
Support to start using the system for Label printing system Arunwit Isarapongporn
14:17 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Support installation for power supply and LAN cable for 20 points Arunwit Isarapongporn
14:16 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Support installation for power supply and LAN cable for 20 points Arunwit Isarapongporn
14:15 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Support installation for power supply and LAN cable for 20 points Arunwit Isarapongporn
14:14 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Support installation for power supply and LAN cable for 20 points Arunwit Isarapongporn
09:35 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #95: Support installation for power supply and LAN cable for 20 points
Layout line of H9J Arunwit Isarapongporn
09:35 ASIAN STANLEY. INTERNATIONAL LIMITED. 1.00 hour (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Arunwit Isarapongporn
09:28 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #95: Support installation for power supply and LAN cable for 20 points
[08/11/2023]
- Setup server for label printer system
- Setting printer name and IP Address
Arunwit Isarapongporn
09:28 ASIAN STANLEY. INTERNATIONAL LIMITED. 1.00 hour (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Arunwit Isarapongporn
08:57 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #95: Support installation for power supply and LAN cable for 20 points
[03/11/2023]
- Install the light rail And the LAN cable above the ceiling is already complete.
- The lighting contr...
Arunwit Isarapongporn
08:57 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Arunwit Isarapongporn
09:23 NTPT COMPANY LIMITED. Project progress work #159 (In Progress): ConMas i-Reporter teaching for NTPT staff
The training schedule has changed as follows.
• 21 Nov 2023 08:50 – 16:50
• 22 Nov 2023 08:50 – 16:50
• ...
Arunwit Isarapongporn
09:23 NTPT COMPANY LIMITED. 1.00 hour (Project progress work #159 (Closed): ConMas i-Reporter teaching for NTPT staff)
Arunwit Isarapongporn
08:45 ASIAN STANLEY. INTERNATIONAL LIMITED. Sales support #36: UPS can not use in some position at LINE model H9J
[31/10/2023]
- Maker BCN UPS can install UPS model 100 VCA, the remaining number to be installed is 9 units in line ...
Arunwit Isarapongporn
08:45 ASIAN STANLEY. INTERNATIONAL LIMITED. 1.00 hour (Sales support #36 (Closed): UPS can not use in some position at LINE model H9J )
Arunwit Isarapongporn
 