Arunwit Isarapongporn's activity

From 24 Oct 2023 to 02 Nov 2023

27 Oct 2023

10:08 ASIAN STANLEY. INTERNATIONAL LIMITED. Sales support #36: UPS can not use in some position at LINE model H9J
[27/10/2023]
Maker BCN
- Sent 2 UPS machines that submitted a claim back to ASI.
Arunwit Isarapongporn
09:52 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #8: Support installation for power supply and LAN cable for 50 points
Add document Infrastructure settings list_R1.xlsx Arunwit Isarapongporn
09:50 TOMAS TECH CO., LTD. Sales support #46 (In Progress): Safety training adjustment
Safety training adjustment
Isuzu Engine Manufacturing Co.,(Thailand)LTD
- The latest update has sent a list of ad...
Arunwit Isarapongporn

25 Oct 2023

12:24 SIAM DENSO MANUFACTURING CO., LTD. Problem-Bug #78 (Confirmation request): Found problem about the alarm of sequnce
[21/10/23]
Solved the problem of Alarm of sequence for all 8 lines.
Arunwit Isarapongporn
12:18 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #95 (In Progress): Support installation for power supply and LAN cable for 20 points
[25/10/23]
-Survey the area where the printer, electrical cabinet, LAN cabinet, and wire rails are installed above t...
Arunwit Isarapongporn
12:11 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work #8: Support installation for power supply and LAN cable for 50 points
[24/10/23]
-Setup IP address and setting application for all remaining Handy terminal devices.
-The setup printer n...
Arunwit Isarapongporn
 