FTS AUTOMOTIVE (THAILAND) CO.,LTD 07 Aug 2024 Phatthadon Inthachot Design Project progress work #687: Network Diagram Network drawing 8.00 Actions
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. 07 Aug 2024 Jidapha Mangkhachot Development Project progress work #470: Packing List System fix program bugs 8.00 Actions
OTICS (THAILAND) CO., LTD. 07 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Coding receive power meter log file 8.00 Actions
OTICS (THAILAND) CO., LTD. 07 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Coding receive power meter log file 8.00 Actions
LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 07 Aug 2024 Thanthima Phaengkham Development Project progress work #491: PICS - Version upgrade development support [Task] LAT - PICS- Conversion and Documents Creation 8/26 8.00 Actions
JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 06 Aug 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
ASIAN STANLEY. INTERNATIONAL LIMITED. 06 Aug 2024 Arunwit Isarapongporn Installation Problem-Bug #74: Request to add 2 access points on the low signal area. Wiring is also need. Installation of access points in mold rooms 8.00 Actions
LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 06 Aug 2024 Thanthima Phaengkham Development Project progress work #489: SALE - Operation test confirmation/Specification creation [Task] LAT - SALE - Operation test confirmation/Specification creation 6/29 8.00 Actions
LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 06 Aug 2024 Thanthima Phaengkham Development Project progress work #488: STEP - Operation test confirmation/Specification creation [Task] LAT - STEP - Operation test confirmation/Specification creation 6/29 8.00 Actions
LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 06 Aug 2024 Thanthima Phaengkham Development Project progress work #487: REPO - Operation test confirmation/Specification creation [Task] LAT - REPO - Operation test confirmation/Specification creation 6/29 8.00 Actions
LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 06 Aug 2024 Thanthima Phaengkham Development Project progress work #486: CYLC - Operation test confirmation/Specification creation [Task] LAT - CYLC - Operation test confirmation/Specification creation 6/24 8.00 Actions
TOMAS TECH CO., LTD. 06 Aug 2024 Phatthadon Inthachot Meeting Sales support #684: HAMASHO AMR Concept Survey area for AMR 8.00 Actions
ASIAN STANLEY. INTERNATIONAL LIMITED. 06 Aug 2024 Soraya Norasing Installation Project progress work #674: [Installation]Process Control System phase2 trainning user (process : mold, dicer, app, classify) and meeting หummary of problems and additional solutions 8.00 Actions
NTPT COMPANY LIMITED. 06 Aug 2024 Kittisak Isarapongporn Installation Project progress work #673: [Settings] Asprova implementation Install the asprova but found the problem about expired license. 3.00 Actions
YAMATO ELECTRIC (THAILAND) CO., LTD. 06 Aug 2024 Kittisak Isarapongporn Meeting Project progress work #608: [Documentation] Get requirements of project 5.00 Actions
ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 06 Aug 2024 Thiraporn Amornsirinukorh Development Project progress work #689: [Coding] Warehouse management system PHP Linkage APIs api linkage endpoints inbound / outbound 8.00 Actions
ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 06 Aug 2024 Thiraporn Amornsirinukorh Development Project progress work #689: [Coding] Warehouse management system PHP Linkage APIs api linkage endpoints 8.00 Actions
OTICS (THAILAND) CO., LTD. 06 Aug 2024 Nattapol Poeam Development Project progress work #688: [ Task ] Coding C# Transfer data PLC to DB DB and stored procedure design 8.00 Actions
THAI METALTECH CO., LTD. 06 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed 3 Approved function schedule inbound permission generate pdf 8.00 Actions
OTICS (THAILAND) CO., LTD. 06 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
TOMAS TECH CO., LTD. 06 Aug 2024 Konlawat Saechee Meeting Sales support #684: HAMASHO AMR Concept Site survey 8.00 Actions
THAI METALTECH CO., LTD. 06 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Development. 8.00 Actions
LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 06 Aug 2024 Kamol Anekchatnuntakool Development Project progress work #662: PICS - Version upgrade development support handy terminal Modify HT Software. 8.00 Actions
THAI METALTECH CO., LTD. 06 Aug 2024 Worawit Khantamool Development Project progress work #668: Upgrade web interface # Schedule - Inbound Schedule Production (95%) 8.00 Actions
OTICS (THAILAND) CO., LTD. 06 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Coding receive power meter log file 8.00 Actions