Project Date User Activity Issue Comment Hours
DAIFUKU (THAILAND) LTD. 24 Jun 2024 Nattapol Poeam Installation Project progress work #643: [Area1] Camera control system Installation camera system area 1 8.00 Actions
DAIFUKU (THAILAND) LTD. 10 May 2024 Panupong Raksakit Installation Project progress work #473: Prepare equipment for installation for Area1 Installation for Area 1 8.00 Actions
DAIFUKU (THAILAND) LTD. 09 May 2024 Panupong Raksakit Installation Project progress work #473: Prepare equipment for installation for Area1 Installation for Area 1 8.00 Actions
DAIFUKU (THAILAND) LTD. 08 May 2024 Panupong Raksakit Installation Project progress work #473: Prepare equipment for installation for Area1 Installation for Area 1 8.00 Actions
DAIFUKU (THAILAND) LTD. 07 May 2024 Panupong Raksakit Installation Project progress work #473: Prepare equipment for installation for Area1 Installation for Area 1 8.00 Actions
DAIFUKU (THAILAND) LTD. 03 May 2024 Nattapol Poeam Installation Project progress work #64: [Area1]Camera control system Installation camera system 8.00 Actions
DAIFUKU (THAILAND) LTD. 03 May 2024 Panupong Raksakit Installation Project progress work #474: [Area1]Camera control system Installation Mechanical 8.00 Actions
DAIFUKU (THAILAND) LTD. 02 May 2024 Nattapol Poeam Installation Project progress work #64: [Area1]Camera control system Installation camera system 8.00 Actions
DAIFUKU (THAILAND) LTD. 02 May 2024 Panupong Raksakit Installation Project progress work #474: [Area1]Camera control system Installation Mechanical 8.00 Actions
DAIFUKU (THAILAND) LTD. 01 May 2024 Nattapol Poeam Installation Project progress work #64: [Area1]Camera control system Installation camera system 8.00 Actions
DAIFUKU (THAILAND) LTD. 30 Apr 2024 Nattapol Poeam Installation Project progress work #406: Prepare equipment for installation for Area1 Wiring and assy equipment 8.00 Actions
DAIFUKU (THAILAND) LTD. 30 Apr 2024 Panupong Raksakit Installation Project progress work #473: Prepare equipment for installation for Area1 Prepare items for installation at the work site. 8.00 Actions
DAIFUKU (THAILAND) LTD. 29 Apr 2024 Nattapol Poeam Installation Project progress work #406: Prepare equipment for installation for Area1 Wiring and assy equipment 8.00 Actions
DAIFUKU (THAILAND) LTD. 29 Apr 2024 Panupong Raksakit Installation Project progress work #473: Prepare equipment for installation for Area1 Prepare items for installation at the work site. 8.00 Actions
DAIFUKU (THAILAND) LTD. 26 Apr 2024 Panupong Raksakit Installation Project progress work #473: Prepare equipment for installation for Area1 Prepare items for installation at the work site. 8.00 Actions
DAIFUKU (THAILAND) LTD. 25 Apr 2024 Nattapol Poeam Installation Project progress work #406: Prepare equipment for installation for Area1 Site survey before installation 8.00 Actions
DAIFUKU (THAILAND) LTD. 25 Apr 2024 Panupong Raksakit Meeting Project progress work #473: Prepare equipment for installation for Area1 Meeting 8.00 Actions
DAIFUKU (THAILAND) LTD. 22 Apr 2024 Nattapol Poeam Installation Project progress work #406: Prepare equipment for installation for Area1 Prepare quipment 4.00 Actions
DAIFUKU (THAILAND) LTD. 22 Apr 2024 Nattapol Poeam Installation Project progress work #406: Prepare equipment for installation for Area1 Prepare quipment 4.00 Actions
DAIFUKU (THAILAND) LTD. 17 Feb 2024 Suchin Viyasing Installation Project progress work #431: Wiring on the cabinet 18 set. Wiring cable in the cabinet 8.00 Actions
DAIFUKU (THAILAND) LTD. 15 Feb 2024 Suchin Viyasing Installation Project progress work #431: Wiring on the cabinet 18 set. Wiring cable in the cabinet 8.00 Actions
DAIFUKU (THAILAND) LTD. 14 Feb 2024 Suchin Viyasing Installation Project progress work #431: Wiring on the cabinet 18 set. Wiring cable in the cabinet 8.00 Actions
DAIFUKU (THAILAND) LTD. 13 Feb 2024 Suchin Viyasing Installation Project progress work #431: Wiring on the cabinet 18 set. Wiring cable in the cabinet 8.00 Actions
DAIFUKU (THAILAND) LTD. 12 Feb 2024 Suchin Viyasing Installation Project progress work #431: Wiring on the cabinet 18 set. 8.00 Actions
DAIFUKU (THAILAND) LTD. 09 Feb 2024 Suchin Viyasing Installation Project progress work #431: Wiring on the cabinet 18 set. Sick 8.00 Actions