Project

General

Profile

Spent time

Filters

Apply Clear

Hours: 1105.50

Project Date User Activity Issue Comment Hours
Thai Metaltech Co.,Ltd 21 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Installation software on site. 8.00 Actions
Thai Metaltech Co.,Ltd 20 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Final test on the web and handy presentation with the client, and bug fixing. 8.00 Actions
Thai Metaltech Co.,Ltd 20 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Testing and meeting present with TMC. 8.00 Actions
Thai Metaltech Co.,Ltd 19 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Internal test with handy and fix bug 8.00 Actions
Thai Metaltech Co.,Ltd 19 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 7.00 Actions
Thai Metaltech Co.,Ltd 16 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 8.00 Actions
Thai Metaltech Co.,Ltd 16 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed Production PartRequest And Test Inbound Production cut material in bom type lotsize and production sdi 8.00 Actions
Thai Metaltech Co.,Ltd 15 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Production Bom Fg,SDI,FG and SDI Test Outbound delivery 8.00 Actions
Thai Metaltech Co.,Ltd 15 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Test and fixed outbound and lotsize function. 4.00 Actions
Thai Metaltech Co.,Ltd 14 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Test and fixed bug Outbound delivery 5.00 Actions
Thai Metaltech Co.,Ltd 14 Aug 2024 Ronnagon Kongsuwan Meeting Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Meeting with tmc finish design bom and preview web pegasus 3.00 Actions
Thai Metaltech Co.,Ltd 14 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Test outbound delivery and meeting with TMC. 3.00 Actions
Thai Metaltech Co.,Ltd 13 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Inbound Schedule Production SDI - Outbound Material By Bom Test Delivery Outbound Schedule 8.00 Actions
Thai Metaltech Co.,Ltd 13 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 4.00 Actions
Thai Metaltech Co.,Ltd 10 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed Inbound Schedule Production Fg - Outbound Material By Bom 8.00 Actions
Thai Metaltech Co.,Ltd 10 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 5.00 Actions
Thai Metaltech Co.,Ltd 09 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and testing. 2.00 Actions
Thai Metaltech Co.,Ltd 09 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed stored procedures for BOM in inbound to manage outbound material and fixed bugs in the inbound material PO stored procedure. 8.00 Actions
Thai Metaltech Co.,Ltd 08 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed table Bom Page Bom in master data 8.00 Actions
Thai Metaltech Co.,Ltd 07 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Test Fix bug Function Inbound Schedule Material 8.00 Actions
Thai Metaltech Co.,Ltd 07 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Development. 8.00 Actions
Thai Metaltech Co.,Ltd 06 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed 3 Approved function schedule inbound permission generate pdf 8.00 Actions
Thai Metaltech Co.,Ltd 06 Aug 2024 Taweesak Prumvised Development Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Development. 8.00 Actions
Thai Metaltech Co.,Ltd 05 Aug 2024 Taweesak Prumvised Meeting Project progress work #604: [Coding] Warehouse management system handyterminal Java Phase01 Meeting and develop. 8.00 Actions
Thai Metaltech Co.,Ltd 05 Aug 2024 Ronnagon Kongsuwan Development Project progress work #650: [Coding] Warehouse management system Web App PHP Pegasus Phase1 Developed and completed New Design Page Outbound Schedule Delivery Manual Generate New requirement client. 8.00 Actions