Tomas Tech Co.,Ltd. 10 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai ConMas Gateway for get data between FormA and FormB 8.00 Actions
Tomas Tech Co.,Ltd. 10 Oct 2024 Phatthadon Inthachot Make document Project progress work #806: Estimate cost Estimate cost for AH brake CNC monitering 8.00 Actions
Tomas Tech Co.,Ltd. 10 Oct 2024 Soraya Norasing Meeting Project progress work #622: For internal meeting and other internal meeting with K.nack about ASI project , Internal meeting with k.pum about php 3.00 Actions
Tomas Tech Co.,Ltd. 09 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai ConMas Gateway for get data between FormA and FormB 8.00 Actions
Tomas Tech Co.,Ltd. 09 Oct 2024 Phatthadon Inthachot Make document Project progress work #806: Estimate cost Estimate cost for AH brake CNC monitering 8.00 Actions
Tomas Tech Co.,Ltd. 09 Oct 2024 Phatthadon Inthachot Taking Day off Project progress work #523: Phatthadon Inthachot Taking Day off January-December 2024 Personal Leave 8.00 Actions
Tomas Tech Co.,Ltd. 08 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai Handy A-500 and app i-Reporter connected demo of MAST-T 8.00 Actions
Tomas Tech Co.,Ltd. 07 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai Handy A-500 and app i-Reporter connected demo of MAST-T 8.00 Actions
Tomas Tech Co.,Ltd. 07 Oct 2024 Soraya Norasing Meeting Project progress work #622: For internal meeting and other 1. Installation & onsite at NTPT, 2. meeting with NTMT about modify HT input, 3. meeting with K.sakda ASI about request K.ostu for modify process control system, 4. meeting with K.pug about how to share caladar 8.00 Actions
Tomas Tech Co.,Ltd. 05 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai Modify i-Reporter ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 04 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai Modify i-Reporter ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 04 Oct 2024 Nattapol Poeam Design Sales support #730: [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system Summarize cost and make concept 8.00 Actions
Tomas Tech Co.,Ltd. 04 Oct 2024 Soraya Norasing Meeting Project progress work #622: For internal meeting and other meeting with K.oil about issue i-reporter, meeting with customer ASI about schedule project, support user ASI about check data random check and reset senser printer 8.00 Actions
Tomas Tech Co.,Ltd. 03 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai Modify i-Reporter ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 03 Oct 2024 Nattapol Poeam Design Project progress work #443: Copeland (Thailand) Co., Ltd. ( Emerson ) Make concept and summarize cost 8.00 Actions
Tomas Tech Co.,Ltd. 02 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai Modify i-Reporter ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 02 Oct 2024 Phatthadon Inthachot Taking Day off Project progress work #523: Phatthadon Inthachot Taking Day off January-December 2024 Sick leave 8.00 Actions
Tomas Tech Co.,Ltd. 02 Oct 2024 Soraya Norasing Meeting Project progress work #622: For internal meeting and other Meeting Asprova system at NTPT, Support user ASI about printer 8.00 Actions
Tomas Tech Co.,Ltd. 01 Oct 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai Modify i-Reporter ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 30 Sep 2024 Arunwit Isarapongporn Development Project progress work #284: ConMas i-Reporter create teaching document into Thai Modify i-Reporter ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 30 Sep 2024 Soraya Norasing Meeting Project progress work #622: For internal meeting and other 1.00 Actions
Tomas Tech Co.,Ltd. 27 Sep 2024 Arunwit Isarapongporn Installation Project progress work #284: ConMas i-Reporter create teaching document into Thai Installation i-Reporter for Demo ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 26 Sep 2024 Arunwit Isarapongporn Installation Project progress work #284: ConMas i-Reporter create teaching document into Thai Installation i-Reporter for Demo ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 25 Sep 2024 Arunwit Isarapongporn Installation Project progress work #284: ConMas i-Reporter create teaching document into Thai Installation i-Reporter for Demo ConMas Gateway 8.00 Actions
Tomas Tech Co.,Ltd. 25 Sep 2024 Nattapol Poeam Design Sales support #730: [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system Make concept 8.00 Actions