30 Sep 2023

17:31 Project progress work #7 (Closed): Development of stock management function for BT-A500 handy terminal
Ryo Nozaki
17:02 Project progress work #7 (Confirmation request): Development of stock management function for BT-A500 handy terminal
Soraya Norasing
16:59 Project progress work #7 (In Progress): Development of stock management function for BT-A500 handy terminal
Implemented Login and menu functions and completed UT.
Tomorrow I plan to design and implement the Inbound screen.
Ryo Nozaki user
16:34 Project progress work #7 (Closed): Development of stock management function for BT-A500 handy terminal
“Problem” It became impossible to scan some QR codes on the Inbound screen of the handy terminal.
“Cause” The 10th ...
Ryo Nozaki user
 