21 Nov 2023 Yutthapong Sricha Meeting Project progress work #166: IoT monitoring at web screen development PHP 1.00 Actions
21 Nov 2023 Kamol Anekchatnuntakool Development Project progress work #247: [Coding]Drink order system C# Develop Drink order system. 8.00 Actions
20 Nov 2023 Kamol Anekchatnuntakool Development Project progress work #247: [Coding]Drink order system C# Develop Drink order system. 8.00 Actions
20 Nov 2023 Suchin Viyasing Development Project progress work #241: Learning Keyence PLC 8.00 Actions
18 Nov 2023 Suchin Viyasing Development Project progress work #241: Learning Keyence PLC Learning Plc Keyence 8.00 Actions
16 Nov 2023 Nattapol Poeam Design Project progress work #233: Edit the data transmission concept of the Demo-Box line notify alert job. Revised concept about format PLC send to PLC and Data memory 2.00 Actions
16 Nov 2023 Nattapol Poeam Development Project progress work #233: Edit the data transmission concept of the Demo-Box line notify alert job. Support K.Santi and K.Kamol test Demo-Kit 3.00 Actions
16 Nov 2023 Nattapol Poeam Meeting Project progress work #233: Edit the data transmission concept of the Demo-Box line notify alert job. Meeting about change new concept send and receive data between PC <> PLC 2.00 Actions
09 Nov 2023 Suchin Viyasing Development Project progress work #203: Test Program & Make document Design drawing 8.00 Actions
08 Nov 2023 Suchin Viyasing Development Project progress work #203: Test Program & Make document Make document 8.00 Actions
08 Nov 2023 Suchin Viyasing Make document Project progress work #203: Test Program & Make document Leaning function PLC Mitsubishi & Make document 8.00 Actions
08 Nov 2023 Suchin Viyasing Development Project progress work #196: Test Program Leaning function PLC Mistubishi 8.00 Actions
08 Nov 2023 Suchin Viyasing Make document Project progress work #212: Check Relay contactor from supplier Request price for relay from supplier. 8.00 Actions
08 Nov 2023 Suchin Viyasing Development Project progress work #191: Test Program Leaning function PLC Mistubishi 8.00 Actions
08 Nov 2023 Suchin Viyasing Development Project progress work #195: Test Program 8.00 Actions
07 Nov 2023 Suchin Viyasing Development Project progress work #193: Test Program 8.00 Actions
07 Nov 2023 Suchin Viyasing Development Project progress work #192: Test Program & Outside 8.00 Actions
07 Nov 2023 Suchin Viyasing Development Project progress work #194: Test Program & Outside Leaning function PLC Mistubishi & Outside 8.00 Actions
06 Nov 2023 Suchin Viyasing Make document Project progress work #212: Check Relay contactor from supplier Request price for relay from supplier. 8.00 Actions
04 Nov 2023 Suchin Viyasing Development Project progress work #196: Test Program 8.00 Actions
04 Nov 2023 Arunwit Isarapongporn Development Sales support #48: Redmine email notifications Redmine email notifications setting 8.00 Actions
04 Nov 2023 Suchin Viyasing Development Project progress work #193: Test Program 8.00 Actions
04 Nov 2023 Arunwit Isarapongporn Development Sales support #48: Redmine email notifications 1.00 Actions
03 Nov 2023 Suchin Viyasing Development Project progress work #195: Test Program Leaning function PLC Mistubishi 8.00 Actions
02 Nov 2023 Suchin Viyasing Development Project progress work #194: Test Program & Outside Leaning function PLC Mistubishi & Outside 8.00 Actions