Project

General

Profile

Actions

Issues

Filters

Apply Clear

Estimated time: 6054.00 Spent time: 3451.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
730 Sales support In Progress Normal [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system Nattapol Poeam 50.00 28.00 23 Sep 2024 12:00 Actions
726 Parent project In Progress Normal [PJ*****] Mobile project for NFC smart card and calling system for mobile Ryo Nozaki 80.00 256.00 06 Dec 2024 10:36 Actions
722 Sales support In Progress Normal MCCT Make concept and summary cost Nattapol Poeam 50.00 8.00 16 Sep 2024 16:57 Actions
719 Sales support In Progress Normal Traceability new line for ADVICS Nattapol Poeam 100.00 48.00 16 Sep 2024 16:51 Actions
718 Project progress work In Progress Normal Machine operation monitoring for KAWASAKI Nattapol Poeam 100.00 56.00 16 Sep 2024 16:57 Actions
714 Project progress work New Normal For internal meeting and other Panthita Roekdee 1096.00 1592.00 20 Mar 2025 16:49 Actions
671 Project progress work In Progress Normal [Meeting] Interview and other Kittisak Isarapongporn 40.00 52.00 02 Sep 2024 00:39 Actions
644 Project progress work In Progress Normal [ Task ] Internal management Nattapol Poeam 1000.00 44.00 11 Jul 2024 20:36 Actions
629 Project progress work In Progress Normal [MAST] Improve pegasus Worawit Khantamool 80.00 212.00 28 Nov 2024 15:38 Actions
622 Project progress work In Progress Normal For internal meeting and other Soraya Norasing 100.00 172.00 30 Sep 2024 23:42 Actions
602 Project progress work New Normal DEMO Print Bluetooth 20.00 8.00 05 Jun 2024 10:04 Actions
597 Sales support In Progress Normal [ On-site ] Meeting about New project IoT Nattapol Poeam 74.00 60.00 25 Dec 2024 23:46 Actions
533 Parent project New Normal [PJ******]General and administrative expenses Ryo Nozaki 7599.00 2920.80 22 Aug 2025 15:13 Actions
532 Parent project New Normal [PJ******] Internal development project Ryo Nozaki 3773.00 3371.50 27 Jun 2025 17:29 Actions
525 Project progress work New Normal Priroj Neamjarn Taking Day off January-December 2024 Priroj Neamjarn 80.00 0.00 04 May 2024 17:22 Actions
524 Project progress work New Normal Konlawat Saechee Taking Day off January-December 2024 Konlawat Saechee 160.00 120.00 20 Dec 2024 10:10 Actions
523 Project progress work New Normal Phatthadon Inthachot Taking Day off January-December 2024 Phatthadon Inthachot 80.00 24.00 04 May 2024 17:22 Actions
521 Project progress work New Normal Ronnagon Kongsuwan Taking Day off January-December 2024 Ronnagon Kongsuwan 80.00 4.00 04 May 2024 17:22 Actions
520 Project progress work New Normal Thanthima Phaengkham Taking Day off January-December 2024 Thanthima Phaengkham 80.00 8.00 04 May 2024 17:22 Actions
517 Project progress work New Normal Panupong Raksakit Taking Day off January-December 2024 Panupong Raksakit 80.00 40.00 04 May 2024 17:22 Actions
516 Project progress work New Normal Narupot Muangsiri Taking Day off January-December 2024 80.00 16.00 04 May 2024 17:22 Actions
515 Project progress work New Normal Nattapol Poeam Taking Day off January-December 2024 Nattapol Poeam 80.00 104.00 04 May 2024 17:22 Actions
513 Project progress work New Normal Nongnut Tophimai Taking Day off January-December 2024 Nongnut Tophimai 80.00 0.00 04 May 2024 17:22 Actions
511 Project progress work New Normal Arunwit Isarapongporn Taking Day off January-December 2024 Arunwit Isarapongporn 80.00 80.00 04 May 2024 17:22 Actions
510 Project progress work New Normal Anek Sanohkham Taking Day off January-December 2024 Anek Sanohkham 80.00 0.00 04 May 2024 17:22 Actions
(26-50/62) Per page: 25, 50, 100