Project

General

Profile

For internal project work assignment report without Nozaki

« October | December »

Apply Clear

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
44

27

28

29

30

31

Sales support #732: [ Make concept & Summary co... Sales support #732: [ Make concept & Summary cost ] Line operation monitoring

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 25 Sep 2024
Due date: 31 Oct 2024
Assignee: Nattapol Poeam
Priority: Normal
Sales support #730: [ Make concept & Summary co... Sales support #730: [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 23 Sep 2024
Due date: 31 Oct 2024
Assignee: Nattapol Poeam
Priority: Normal
Sales support #719: Traceability new line for A... Sales support #719: Traceability new line for ADVICS

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 01 Aug 2024
Due date: 31 Oct 2024
Assignee: Nattapol Poeam
Priority: Normal
Project progress work #718: Machine operation monitorin... Project progress work #718: Machine operation monitoring for KAWASAKI

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 16 Sep 2024
Due date: 31 Oct 2024
Assignee: Nattapol Poeam
Priority: Normal

1

Project progress work #862: AHT CNC Montoring system Project progress work #862: AHT CNC Montoring system

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 01 Nov 2024
Due date: 28 Dec 2024
Assignee: Nattapol Poeam
Priority: Normal

2

45

3

4

5

6

7

8

9

46

10

11

12

13

14

15

16

47

17

Sales support #798: Site survey customer for ne... Sales support #798: Site survey customer for new project

Project: TOMAS TECH CO., LTD.
Status: New
Start date: 17 Nov 2024
Due date: 27 Dec 2024
Assignee: Phatthadon Inthachot
Priority: Normal

18

Project progress work #806: Estimate cost Project progress work #806: Estimate cost

Project: TOMAS TECH CO., LTD.
Status: New
Start date: 18 Nov 2024
Due date: 27 Dec 2024
Assignee: Phatthadon Inthachot
Priority: Normal

19

20

21

22

23

48

24

25

26

27

Project progress work #833: [TMS-Calling] Web development. Project progress work #833: [TMS-Calling] Web development.

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 27 Nov 2024
Due date: 14 Dec 2024
Assignee: Worawit Khantamool
Priority: Normal

28

29

30

issue beginning this day issue ending this day issue beginning and ending this day