Activity
From 06 May 2025 to 15 May 2025
13 May 2025
- 09:32 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (12/05) Update form NTN(rev.5), meeting about project Sumitomo
- 09:29 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (09/05) Sick leave
- 09:26 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (08/05) Training i-Reporter - Topre
- 09:25 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (07/05) Meeting with Minebea, Update form NTN(rev.5), Meeting with Sumitomo, Training plan i-Reporter for Topre
12 May 2025
- 22:15 8.00 hours (Project progress work #671 (In Progress): [Meeting] Interview and other)
- 22:14 8.00 hours (Project progress work #671 (In Progress): [Meeting] Interview and other)
07 May 2025
- 11:20 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (06/05)Support i-Reporter, Meeting with NMT
- 11:19 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (05/05) Sick leave
- 11:19 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (02/05)Support i-Reporter
- 11:18 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (30/04) Create i-Reporter form-Sumitomo (3/3)
- 11:18 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (29/04) Create i-Reporter form-Sumitomo (2/3), Meeting with FNTC, Meeting with Thaitinplate
- 11:17 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (28/04) Create i-Reporter form-Sumitomo (1/3)
- 11:16 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (25/04)Support i-Reporter, Meeting with NMT
- 11:16 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (24/04) Create i-Reporter form-NMT (rev.4)
- 11:15 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (23/04)Training i-Reporter-Topre
- 11:14 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (22/04) Create i-Reporter form-NMT (rev.4)
- 11:13 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (21/04) Support i-Reporter, On-side NMT
- 11:12 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (18/04) Create i-Reporter form-NMT (4/4), On-side Pioneer Electronics
- 11:11 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (17/04) Create i-Reporter form-NMT (3/4), Meeting with Sumitomo
- 11:11 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (11/04) Create i-Reporter form-NMT (2/4), Meeting with Techno-mental, Meeting with Minebea
- 11:09 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (10/04) Create i-Reporter form-NMT (1/4), Training Nichiden on Asok office
- 11:08 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (09/04) Create i-Reporter form-Sumitomo (3/3)
- 11:07 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (08/04) Create i-Reporter form-Sumitomo (2/3)
- 11:07 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (07/04) Create i-Reporter form-Sumitomo (1/3)
- 11:05 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (04/04) Leave of absence
- 11:05 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (03/04) Leave of absence
Also available in: Atom