04 Dec 2024
- 13:13 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Create i-Reporter form, Meeting with customer
- 08:04 8.00 hours (Project progress work #833 (In Progress): [TMS-Calling] Web development.)
- Web theme migration (2/10)
03 Dec 2024
- 16:04 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter, Create i-Reporter form
02 Dec 2024
- 17:12 3.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Testing all, schedule function.
- 13:35 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter, Create i-Reporter form
- 13:34 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (30/11)Create i-Reporter form (SCMP) (2/5)
- 08:40 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer and PCB wiring
- 08:40 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer and PCB wiring
- 08:36 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 08:36 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 08:36 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 08:35 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 08:32 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- wiring and assemble
- 08:38 8.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
- wiring assemble program
- 08:37 8.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
- wiring assemble program
- 08:34 8.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
- wiring assemble and program test
- 08:34 8.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
- wiring assemble and program test
30 Nov 2024
- 17:19 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Edit show all and add schedule.
- 15:50 8.00 hours (Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI)
- Meeting about pokayoke system
- 15:44 8.00 hours (Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI)
- Meeting about pokayoke system
- 14:49 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (29/11)Create i-Reporter form (SCMP) (1/5)
29 Nov 2024
- 20:12 8.00 hours (Sales support #695 (Closed): Concept install label print and collection signal machine)
- table stand label printer
- 20:05 4.00 hours (Sales support #695 (Closed): Concept install label print and collection signal machine)
- Drawing table stand label printer
- 20:06 4.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
- Drawing
- 19:57 8.00 hours (Sales support #834 (Closed): ADVICS Table Server)
- 3D design
28 Nov 2024
- 17:42 2.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add show all.
- 15:30 4.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Fixed upload and download image.
- 15:30 8.00 hours (Project progress work #833 (In Progress): [TMS-Calling] Web development.)
- Web theme migration (1/10)
- 15:14 8.00 hours (Project progress work #832 (Closed): Demo Pegasus)
- 3D Production Monitoring (3/3)
- 15:14 8.00 hours (Project progress work #832 (Closed): Demo Pegasus)
- 3D Production Monitoring (2/3)
- 15:14 8.00 hours (Project progress work #832 (Closed): Demo Pegasus)
- 3D Production Monitoring (1/3)
- 15:10 8.00 hours (Project progress work #832 (Closed): Demo Pegasus)
- Demo Dashboard (3/3)
- 15:09 8.00 hours (Project progress work #832 (Closed): Demo Pegasus)
- Demo Dashboard (2/3)
- 15:09 8.00 hours (Project progress work #832 (Closed): Demo Pegasus)
- Demo Dashboard (1/3)
- 09:23 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- (27/11)Support i-Reporter, Create i-Reporter form(Minebea)
- 08:20 8.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
- Meeting Assemble and Wiring
- 08:19 8.00 hours (Project progress work #811 (Closed): keyence Demo kit No.259)
- Assemble and Wiring
- 08:17 8.00 hours (Project progress work #524 (New): Konlawat Saechee Taking Day off January-December 2024)
- Take leave
26 Nov 2024
- 16:56 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add dowload image and test overall function.
- 12:31 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter, Create i-Reporter form