17 Nov 2024
- 23:58 8.00 hours (Project progress work #804 (Closed): NTN concept panel)
- Estimate cost
- 23:58 8.00 hours (Project progress work #804 (Closed): NTN concept panel)
- Drawing EE
- 23:31 1.00 hour (Project progress work #646 (Closed): WDT and smartwatch demo project)
- Assign work regarding MAST demo to khun Puk
- 23:28 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.260
- 23:28 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.252
- 23:11 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.259
- 23:10 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.259
- 23:10 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- Estimate cost No.259
- 23:13 8.00 hours (Sales support #711 (Closed): LAZADA Barcode reader systems)
- Estimate cost
- 21:18 8.00 hours (Sales support #798 (New): Site survey customer for new project)
- site survey at HAVI
- 21:01 8.00 hours (Project progress work #523 (New): Phatthadon Inthachot Taking Day off January-December 2024)
- Personal Leave
- 21:00 8.00 hours (Project progress work #523 (New): Phatthadon Inthachot Taking Day off January-December 2024)
- Sick leave
- 18:14 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:12 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:10 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:10 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:09 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:09 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
- 18:08 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3d printer,wiring,assemble,Arduino program
16 Nov 2024
- 17:42 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:42 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:41 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:41 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:41 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:41 8.00 hours (Sales support #710 (Closed): Demo Keyence 4 Set)
- 3D Drawing
- 17:23 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
- 3D Printing Assembly
- 09:57 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
15 Nov 2024
- 17:29 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
14 Nov 2024
- 14:56 8.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Add api preset data.
- 08:52 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
13 Nov 2024
- 08:09 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter, Meeting with customer
12 Nov 2024
- 13:45 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter
- 09:31 2.00 hours (Project progress work #740 (In Progress): [Development] Mobile android device and api development.)
- Edit flow of websocket.
11 Nov 2024
- 15:13 8.00 hours (Project progress work #443 (In Progress): Copeland (Thailand) Co., Ltd. ( Emerson ))
- Make concept and summarize cost
- 15:12 8.00 hours (Sales support #730 (In Progress): [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system)
- Summarize cost and make concept
- 14:57 8.00 hours (Sales support #730 (In Progress): [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system)
- Site survey about confirm position sensor
- 14:51 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:51 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:51 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:51 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:51 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:50 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:50 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:50 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:50 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:49 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:49 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:48 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:48 8.00 hours (Project progress work #515 (New): Nattapol Poeam Taking Day off January-December 2024)
- leave ordination
- 14:09 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter NTPT, Create i-Reporter form
09 Nov 2024
- 23:22 4.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- Meeting Asprova system at NTPT
- 23:18 8.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- Test handy mast for demo with customer
- 23:17 8.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- demo handy with customer nippn at office
08 Nov 2024
- 14:51 8.00 hours (Project progress work #714 (New): For internal meeting and other)
- Support i-Reporter NTPT, Create i-Reporter form