19 Jul 2024

14:29 8.00 hours (Project progress work #670 (Closed): Demo LEGO)
Design Konlawat Saechee
14:28 4.00 hours (Project progress work #670 (Closed): Demo LEGO)
Design LEGO Konlawat Saechee

18 Jul 2024

16:54 8.00 hours (Project progress work #651 (Closed): OTICS Dashboard in mast demo)
Collapse all dashboard pages into a single menu page. Worawit Khantamool

17 Jul 2024

16:45 4.00 hours (Project progress work #651 (Closed): OTICS Dashboard in mast demo)
Edit Dashboard (request K'Ryo) Worawit Khantamool

13 Jul 2024

22:20 8.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
Will check and estimate the modification (move to use server side script) Worawit Khantamool
16:48 8.00 hours (Project progress work #656 (Closed): Demo Develop HT Software for Receive weight data and Send to Printer.)
Demo Develop HT Software for Receive weight data and Send to Printer. Kamol Anekchatnuntakool
13:31 4.00 hours (Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI)
Demo CCTV Konlawat Saechee

12 Jul 2024

16:51 8.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
Item Master Information (backend) Worawit Khantamool
16:44 8.00 hours (Project progress work #656 (Closed): Demo Develop HT Software for Receive weight data and Send to Printer.)
Demo Develop HT Software for Receive weight data and Send to Printer. Kamol Anekchatnuntakool
15:44 8.00 hours (Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI)
Survey area install camera Phatthadon Inthachot
15:42 8.00 hours (Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI)
Test Demo Camera Phatthadon Inthachot
15:41 8.00 hours (Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI)
Survey Phatthadon Inthachot
14:59 4.00 hours (Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI)
Demo CCTV Konlawat Saechee
14:55 8.00 hours (Project progress work #612 (Closed): demo kit safety door system)
Wiring and Setting HF2211 (232 to wifi) Konlawat Saechee

11 Jul 2024

21:56 1.00 hour (Project progress work #622 (In Progress): For internal meeting and other)
Asprova meeting with K.Ryo Soraya Norasing
21:55 1.00 hour (Project progress work #622 (In Progress): For internal meeting and other)
Soraya Norasing
20:37 8.00 hours (Project progress work #644 (In Progress): [ Task ] Internal management)
Onsite meeting about Andon project Nattapol Poeam
20:25 8.00 hours (Project progress work #644 (In Progress): [ Task ] Internal management)
Management task and clear other document Nattapol Poeam
20:27 8.00 hours (Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI)
Make concept Nattapol Poeam
20:13 4.00 hours (Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI)
Demo CCTV Nattapol Poeam
16:58 16.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
Supplier Master Information (Backend), Department Master (Backend) Worawit Khantamool
16:54 8.00 hours (Project progress work #656 (Closed): Demo Develop HT Software for Receive weight data and Send to Printer.)
Demo Develop HT Software for Receive weight data and Send to Printer. Kamol Anekchatnuntakool
16:49 4.50 hours (Project progress work #656 (Closed): Demo Develop HT Software for Receive weight data and Send to Printer.)
Demo Develop HT Software for Receive weight data and Send to Printer. Kamol Anekchatnuntakool
 