29 Jun 2024

17:17 8.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
Outbound Schedule Detail (ฺBackend) And Test case scenarios Worawit Khantamool

28 Jun 2024

16:55 8.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
Custom menu constant active, Inbound Schedule (Backend), Inbound Schedule Detail (Backend), Outbound Schedule (Backend) Worawit Khantamool
15:26 4.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
Soraya Norasing
08:19 8.00 hours (Project progress work #284 (Closed): ConMas i-Reporter create teaching document into Thai)
ConMas i-Reporter create teaching document into Thai Arunwit Isarapongporn
08:18 8.00 hours (Project progress work #284 (Closed): ConMas i-Reporter create teaching document into Thai)
ConMas i-Reporter create teaching document into Thai Arunwit Isarapongporn
08:11 8.00 hours (Project progress work #284 (Closed): ConMas i-Reporter create teaching document into Thai)
ConMas i-Reporter create teaching document into Thai Arunwit Isarapongporn
08:10 8.00 hours (Project progress work #284 (Closed): ConMas i-Reporter create teaching document into Thai)
ConMas i-Reporter create teaching document into Thai Arunwit Isarapongporn
08:10 8.00 hours (Project progress work #284 (Closed): ConMas i-Reporter create teaching document into Thai)
ConMas i-Reporter create teaching document into Thai Arunwit Isarapongporn
08:10 8.00 hours (Project progress work #284 (Closed): ConMas i-Reporter create teaching document into Thai)
ConMas i-Reporter create teaching document into Thai Arunwit Isarapongporn
08:10 8.00 hours (Project progress work #284 (Closed): ConMas i-Reporter create teaching document into Thai)
ConMas i-Reporter create teaching document into Thai Arunwit Isarapongporn
08:09 8.00 hours (Project progress work #284 (Closed): ConMas i-Reporter create teaching document into Thai)
ConMas i-Reporter create teaching document into Thai Arunwit Isarapongporn
07:58 8.00 hours (Project progress work #651 (Closed): OTICS Dashboard in mast demo)
Create Dashboard : Daily hourly bar chart display, Monthly daily bar chart display, Yearly monthly bar chart display,... Worawit Khantamool

26 Jun 2024

17:48 8.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
Inbound Schedule (Backend 95%), Inbound Schedule Detail (Backend 95%) Worawit Khantamool

25 Jun 2024

16:49 8.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
# Master Management => Location Master, User Master, User Credential Master Worawit Khantamool

24 Jun 2024

22:42 3.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
translate pokayoke system Soraya Norasing
22:30 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
Soraya Norasing
17:01 8.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
Create Menu | # Master Management => Item Master, Bucket Quantity, Packing Standard Worawit Khantamool
01:04 8.00 hours (Project progress work #646 (Closed): WDT and smartwatch demo project)
Revise the old store procedure and fix the summary function(problem found about the incorrect data) Kittisak Isarapongporn
00:39 8.00 hours (Project progress work #646 (Closed): WDT and smartwatch demo project)
Create the javascript to display the daily work chart Kittisak Isarapongporn
00:38 8.00 hours (Project progress work #646 (Closed): WDT and smartwatch demo project)
Create new DB store procedure script for daily work chart Kittisak Isarapongporn

23 Jun 2024

15:31 8.00 hours (Project progress work #519 (Closed): Jidapha Mangkhachot Taking Day off January-December 2024)
Personal Leave Jidapha Mangkhachot

22 Jun 2024

18:35 4.00 hours (Project progress work #612 (Closed): demo kit safety door system)
Assemble Konlawat Saechee

21 Jun 2024

16:57 8.00 hours (Project progress work #644 (In Progress): [ Task ] Internal management)
Make document for installation Nattapol Poeam
16:53 8.00 hours (Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI)
Meeting with supplier planet Hikvistion team Nattapol Poeam
16:48 8.00 hours (Project progress work #629 (In Progress): [MAST] Improve pegasus)
Create Menu | # Master Management => Supplier Master, Supplier Master Information, Department Master, Item Master Inf... Worawit Khantamool
 