Activity
From 16 Jun 2024 to 25 Jun 2024
25 Jun 2024
24 Jun 2024
- 22:30 Project progress work #509: Soraya Norasing Taking Day off January-December 2024
- sick leave (stomach ache, gastritis)
- 00:37 Project progress work #646 (Closed): WDT and smartwatch demo project
21 Jun 2024
- 16:56 Project progress work #644 (In Progress): [ Task ] Internal management
- - Document
- Support team
- Fix problem
- Other - 16:53 Project progress work #639: [ concept and estimate cost ] CCTV installation for ANI
- - Spec camera
- Spec server
Next action
27/06/24
- Confrim postion camera at site with K.Khwanchai
18 Jun 2024
- 20:10 Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI
- - Make concept installation CCTV
- Summarize cost