18 Jun 2024
- 20:10 Project progress work #639 (Closed): [ concept and estimate cost ] CCTV installation for ANI
- - Make concept installation CCTV
- Summarize cost
15 Jun 2024
- 14:15 Project progress work #625 (Confirmation request): Setup notebook and install program
- 14:08 Project progress work #624 (Confirmation request): Compatible with A700 Pegasus standard programs
- 14:08 Project progress work #631 (Confirmation request): First day new working
14 Jun 2024
- 09:12 Project progress work #624: Compatible with A700 Pegasus standard programs
- Check all screen compatible with A700
- Scan QR Code.
- Textfield show keyboard with number.
- Edit photo size on ...
11 Jun 2024
- 22:35 Project progress work #622: For internal meeting and other
- meeting with K.Ryo, Keyence, customer about Company introduction.
10 Jun 2024
- 11:11 Project progress work #624: Compatible with A700 Pegasus standard programs
- Testing and checking A500 to compatible with A700.