08 Feb 2024

10:33 Project progress work #433 (Closed): ASI online training safety
Training safety Nattapol Poeam

07 Feb 2024

22:10 Project progress work #421 (Close request): Prepare a demo kit for a meeting at TOPRE.
Kittisak Isarapongporn
22:10 Project progress work #420 (Close request): Go to a meeting at topre
Kittisak Isarapongporn
22:10 Project progress work #419 (Close request): Sick leave to go to hospital
Kittisak Isarapongporn
22:10 Project progress work #418 (Close request): Went to a work meeting in Rayong.
Kittisak Isarapongporn
22:10 Project progress work #416 (Close request): Training FANUC
Kittisak Isarapongporn
22:10 Project progress work #398 (Close request): Make concept and summarize equipment for Interlock system prohect
Kittisak Isarapongporn
22:10 Project progress work #354 (Close request): Lernning PLC Keyence KV-8000
Kittisak Isarapongporn
22:10 Sales support #312 (Close request): Fanuc traning and appointment Fanuc staff
Kittisak Isarapongporn

01 Feb 2024

20:43 Sales support #424 (Closed): YAMATO ELECTRIC (THAILAND) CO.,LTD create proposal and qt
Ryo Nozaki
20:43 Sales support #424 (Closed): YAMATO ELECTRIC (THAILAND) CO.,LTD create proposal and qt
Ryo Nozaki
20:39 Sales support #423 (In Progress): HDK meeting and site survey about traceability system
Ryo Nozaki
20:39 Sales support #423 (In Progress): HDK meeting and site survey about traceability system
Ryo Nozaki
20:38 Sales support #386 (In Progress): Webseminar 2024/2/15
Ryo Nozaki
08:35 Project progress work #421 (Confirmation request): Prepare a demo kit for a meeting at TOPRE.
Prepare a demo kit for a meeting at TOPRE. Suthiwat Banrueangthong
08:34 Project progress work #421 (Closed): Prepare a demo kit for a meeting at TOPRE.
Prepare a demo kit for a meeting at TOPRE. Suthiwat Banrueangthong
08:33 Project progress work #420 (Confirmation request): Go to a meeting at topre
Go to a meeting at topre Suthiwat Banrueangthong
08:32 Project progress work #420 (Closed): Go to a meeting at topre
Go to a meeting at topre Suthiwat Banrueangthong
08:30 Project progress work #419 (Confirmation request): Sick leave to go to hospital
Sick leave to go to hospital Suthiwat Banrueangthong
08:29 Project progress work #419 (Closed): Sick leave to go to hospital
Sick leave to go to hospital Suthiwat Banrueangthong
08:27 Project progress work #418 (Confirmation request): Went to a work meeting in Rayong.
Went to a work meeting in Rayong. Suthiwat Banrueangthong
08:27 Project progress work #418 (Closed): Went to a work meeting in Rayong.
Went to a work meeting in Rayong. Suthiwat Banrueangthong
08:20 Project progress work #416 (Confirmation request): Training FANUC
Training FANUC Suthiwat Banrueangthong
08:19 Project progress work #416 (Closed): Training FANUC
Training FANUC Suthiwat Banrueangthong
08:07 Project progress work #354 (Confirmation request): Lernning PLC Keyence KV-8000
Lernning PLC Keyence KV-8000 Panupong Raksakit
 