18 Nov 2023

16:17 4.00 hours (Sales support #24 (Closed): [FY2023]Common management for Ryo Nozaki)
Meeting with Asprova Ryo Nozaki

17 Nov 2023

16:59 2.00 hours (Project progress work #223 (Closed): Internal check stock)
Internal check stock Nattapol Poeam
16:58 2.00 hours (Project progress work #233 (Closed): Edit the data transmission concept of the Demo-Box line notify alert job.)
Revised concept about format PLC send to PLC and Data memory Nattapol Poeam

16 Nov 2023

16:24 3.00 hours (Project progress work #233 (Closed): Edit the data transmission concept of the Demo-Box line notify alert job.)
Support K.Santi and K.Kamol test Demo-Kit Nattapol Poeam
11:57 2.00 hours (Project progress work #233 (Closed): Edit the data transmission concept of the Demo-Box line notify alert job.)
Meeting about change new concept send and receive data between PC <> PLC Nattapol Poeam

15 Nov 2023

13:17 8.00 hours (Sales support #31 (Closed): [FY2023]Common management for Santi)
PC deverlop Santi Srichankaew
13:14 8.00 hours (Project progress work #165 (Closed): IoT demo kit prepare box for Metarex at Nov)
IoT demo kit prepare box for Metarex at Nov Santi Srichankaew
13:13 8.00 hours (Project progress work #165 (Closed): IoT demo kit prepare box for Metarex at Nov)
IoT demo kit prepare box for Metarex at Nov Santi Srichankaew
10:30 8.00 hours (Sales support #227 (Closed): Webseminar 2023/11/14)
Ryo Nozaki

13 Nov 2023

17:00 3.00 hours (Project progress work #223 (Closed): Internal check stock)
Check stock equipment of project JTEKT,TNF,MAS Nattapol Poeam
08:44 8.00 hours (Sales support #44 (Closed): CKD & Meji Meeting IOT Monitoring system)
Meeting Santi Srichankaew
08:36 8.00 hours (Project progress work #165 (Closed): IoT demo kit prepare box for Metarex at Nov)
Develop Santi Srichankaew

10 Nov 2023

08:15 8.00 hours (Sales support #43 (Closed): Install SR-X300S at Pandora)
File support Santi Srichankaew
 