Estimated time: 18934.00 Spent time: 7923.40

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
730 Sales support In Progress Normal [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system Nattapol Poeam 50.00 28.00 23 Sep 2024 12:00 Actions
728 Project progress work New Normal [ Installation & On-site support] Software installation for IoT Loss analysis MOC Line 1,2 Konlawat Saechee 200.00 0.00 16 Nov 2024 10:46 Actions
726 Parent project In Progress Normal [PJ*****] Mobile project for NFC smart card and calling system for mobile Ryo Nozaki 80.00 256.00 06 Dec 2024 10:36 Actions
722 Sales support In Progress Normal MCCT Make concept and summary cost Nattapol Poeam 50.00 8.00 16 Sep 2024 16:57 Actions
719 Sales support In Progress Normal Traceability new line for ADVICS Nattapol Poeam 100.00 48.00 16 Sep 2024 16:51 Actions
718 Project progress work In Progress Normal Machine operation monitoring for KAWASAKI Nattapol Poeam 100.00 56.00 16 Sep 2024 16:57 Actions
714 Project progress work New Normal For internal meeting and other Panthita Roekdee 1096.00 1592.00 20 Mar 2025 16:49 Actions
698 Parent project New Normal [PJ240025] Install Andon system for monitoring RP-EPS1 #1 PLC plan Nattapol Poeam 410.00 524.50 05 Nov 2025 11:50 Actions
673 Project progress work In Progress Normal [Settings] Asprova implementation Kittisak Isarapongporn 40.00 223.00 25 Dec 2024 18:28 Actions
671 Project progress work In Progress Normal [Meeting] Interview and other Kittisak Isarapongporn 40.00 52.00 02 Sep 2024 00:39 Actions
665 Project progress work New Normal [Setting] Link with i-Reporter and Asprova Arunwit Isarapongporn 100.00 0.00 14 Jul 2024 15:50 Actions
644 Project progress work In Progress Normal [ Task ] Internal management Nattapol Poeam 1000.00 44.00 11 Jul 2024 20:36 Actions
637 Project progress work New Normal [Development] Modify dashboard Worawit Khantamool 16.00 20.00 12 Jun 2024 16:27 Actions
629 Project progress work In Progress Normal [MAST] Improve pegasus Worawit Khantamool 80.00 212.00 28 Nov 2024 15:38 Actions
623 Project progress work In Progress Normal [Installation] Install Raspi and TV monitor Kittisak Isarapongporn 20.00 50.00 25 Dec 2024 18:07 Actions
622 Project progress work In Progress Normal For internal meeting and other Soraya Norasing 100.00 172.00 30 Sep 2024 23:42 Actions
620 Project progress work New Normal Meeting Kittisak Isarapongporn 120.00 200.00 28 Nov 2024 14:05 Actions
614 Project progress work New Normal (Power Meter and CT ) Wiring and Installation Panupong Raksakit 348.00 88.00 16 Nov 2024 12:23 Actions
605 Project progress work New Normal [Coding] Warehouse management system Web app PHP Phase02 Ronnagon Kongsuwan 160.00 98.00 03 Jan 2025 17:29 Actions
602 Project progress work New Normal DEMO Print Bluetooth 20.00 8.00 05 Jun 2024 10:04 Actions
597 Sales support In Progress Normal [ On-site ] Meeting about New project IoT Nattapol Poeam 74.00 60.00 25 Dec 2024 23:46 Actions
594 Project progress work In Progress Normal [Coding] Warehouse management system handyterminal PHP web Ronnagon Kongsuwan 665.00 25 Dec 2024 17:38 Actions
593 Project progress work Close request High [Coding] Warehouse management system handyterminal Java Soraya Norasing 136.00 726.00 17 Jul 2025 17:29 Actions
592 Parent project New High [PJ240023] Stock and process "Pegasus" Phase1 for YAMATO ELECTRIC (THAILAND) CO.,LTD Ryo Nozaki 936.00 1659.00 06 Oct 2025 15:14 Actions
539 Parent project New Normal [PJ240021]Warehouse management system Ryo Nozaki 360.00 1105.50 10 Sep 2025 16:48 Actions