For internal project work assignment report without Nozaki

Apply Clear

Estimated time: 20816.00 Spent time: 6215.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
1303 Project progress work New Normal [Coding] Konlawat Saechee 0.00 16 Jan 2026 10:49 Actions
3329 Project progress work New Normal [Installation&On-site support] Line 5: Installation / Wiring / Config / IO Check Konlawat Saechee 0.00 19 Dec 2025 10:33 Actions
3328 Project progress work New Normal [Installation&On-site support] Line 4: Installation / Wiring / Config / IO Check Konlawat Saechee 0.00 19 Dec 2025 10:32 Actions
3327 Project progress work New Normal [Installation&On-site support] Line 3: Installation / Wiring / Config / IO Check Konlawat Saechee 8.00 0.00 19 Dec 2025 10:31 Actions
3388 Project progress work New Normal [Installation&On-site support] WS controller installation Konlawat Saechee 0.00 24 Dec 2025 13:52 Actions
3334 Project progress work New Normal [Installation&On-site support] Teaching for Go live Konlawat Saechee 0.00 19 Dec 2025 10:38 Actions
3333 Project progress work New Normal [Installation&On-site support] Supports user feedback Konlawat Saechee 0.00 19 Dec 2025 10:37 Actions
3332 Project progress work New Normal [Installation&Onsite support] User Testing & Trial Konlawat Saechee 0.00 19 Dec 2025 10:36 Actions
3331 Project progress work New Normal [Installation&On-site support] Teaching for UT Konlawat Saechee 64.00 0.00 19 Dec 2025 10:36 Actions
3335 Project progress work New Normal [Installation&On-site support] Go live Konlawat Saechee 16.00 0.00 19 Dec 2025 10:39 Actions
6457 Project progress work New Normal [Requirement definition] Kick-off meeting Konlawat Saechee 0.00 06 Feb 2026 11:22 Actions
6458 Project progress work New Normal [Requirement definition] Requirements confirmation Konlawat Saechee 0.00 06 Feb 2026 11:24 Actions
6459 Project progress work New Normal [Internal Design] System Design Konlawat Saechee 0.00 06 Feb 2026 11:34 Actions
6461 Project progress work New Normal [Coding] Hardware pre-shipment confirmation Konlawat Saechee 0.00 06 Feb 2026 11:36 Actions
6460 Project progress work New Normal [Coding] Hardware procurement Konlawat Saechee 0.00 06 Feb 2026 11:35 Actions
6462 Project progress work New Normal [Installation&On-site support] Power Meter installation Konlawat Saechee 0.00 06 Feb 2026 11:39 Actions
6463 Project progress work New Normal [Installation&On-site support] Software installation (PLC) Konlawat Saechee 0.00 06 Feb 2026 11:42 Actions
6466 Project progress work New Normal [Installation&On-site support] Teaching for UT Konlawat Saechee 0.00 06 Feb 2026 11:49 Actions
6465 Project progress work New Normal [Installation&On-site support] Software installation (Web Application) Konlawat Saechee 0.00 06 Feb 2026 11:47 Actions
6464 Project progress work New Normal [Installation&On-site support] Software installation (Application) Konlawat Saechee 0.00 06 Feb 2026 11:44 Actions
6439 Project progress work New Normal [Installation&On-site support] Supports user feedback Konlawat Saechee 0.00 05 Feb 2026 15:51 Actions
6438 Project progress work New Normal [Installation&On-site support] User Testing & Trial Konlawat Saechee 0.00 05 Feb 2026 15:49 Actions
6469 Project progress work New Normal [Installation&On-site support] Teaching for Go live Konlawat Saechee 0.00 06 Feb 2026 11:54 Actions
6468 Project progress work New Normal [Inatallation&On-site support] Supports user feedback Konlawat Saechee 0.00 06 Feb 2026 11:53 Actions
6467 Project progress work New Normal [Installation&On-site support] User Testing & Trial Konlawat Saechee 0.00 06 Feb 2026 11:51 Actions
(251-275/557) Per page: 25, 50, 100