Project

General

Profile

Actions

Issues

Filters

Apply Clear

Estimated time: 56.00 Spent time: 0.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
3330 Project progress work New Normal [Installation&On-site support] Software installation Pattanasak Chaonchom 40.00 0.00 19 Dec 2025 10:38 Actions
3321 Project progress work New Normal [Coding] Validation check Signal & Information Pattanasak Chaonchom 0.00 19 Dec 2025 09:24 Actions
3320 Project progress work New Normal [Coding] WDT Configuration Line 5 Pattanasak Chaonchom 0.00 19 Dec 2025 09:22 Actions
3319 Project progress work New Normal [Coding] Validation check Signal & Information Line 4 Pattanasak Chaonchom 0.00 19 Dec 2025 09:24 Actions
3318 Project progress work New Normal [Coding] WDT Configuration Line 4 Pattanasak Chaonchom 0.00 19 Dec 2025 09:21 Actions
3317 Project progress work New Normal [Coding] Validation check Signal & Information Line 3 Pattanasak Chaonchom 8.00 0.00 19 Dec 2025 09:23 Actions
3316 Project progress work New Normal [Coding] WDT Configuration Line 3 Pattanasak Chaonchom 8.00 0.00 19 Dec 2025 09:19 Actions
1408 Project progress work In Progress Normal [Coding] Windows app & Back-end Pattanasak Chaonchom 392.00 0.00 24 Feb 2026 16:09 Actions
    (1-8/8)

    Also available in: Atom CSV PDF