5

26

27

28

29

30

31

NKT NIPPON KONPO (THAILAND) CO., LTD - Project progress work #866: [Documentation] Get require... Project progress work #866: [Documentation] Get requirements of project

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: New
Start date: 24 Dec 2024
Due date: 31 Jan 2025
Assignee: Kittisak Isarapongporn
Priority: Normal

1

TOPRE (THAILAND) CO., LTD. - Project progress work #1046: [Installation&On-site support] Project progress work #1046: [Installation&On-site support]

Project: TOPRE (THAILAND) CO., LTD.
Status: New
Start date: 01 Feb 2025
Due date: 01 Feb 2025
Assignee: Anek Sanohkham
Priority: Normal
TOPRE (THAILAND) CO., LTD. - Project progress work #1045: [Coding] Project progress work #1045: [Coding]

Project: TOPRE (THAILAND) CO., LTD.
Status: New
Start date: 01 Feb 2025
Due date: 01 Feb 2025
Assignee: Anek Sanohkham
Priority: Normal
TOPRE (THAILAND) CO., LTD. - Project progress work #1044: [Internal Design] Project progress work #1044: [Internal Design]

Project: TOPRE (THAILAND) CO., LTD.
Status: New
Start date: 01 Feb 2025
Due date: 01 Feb 2025
Assignee: Anek Sanohkham
Priority: Normal
TOPRE (THAILAND) CO., LTD. - Project progress work #1043: [Requirement definition] Project progress work #1043: [Requirement definition]

Project: TOPRE (THAILAND) CO., LTD.
Status: New
Start date: 01 Feb 2025
Due date: 01 Feb 2025
Assignee: Anek Sanohkham
Priority: Normal
TOPRE (THAILAND) CO., LTD. - Parent project #1042: [PJ250006] ConMas i-Reporte... Parent project #1042: [PJ250006] ConMas i-Reporter 10 users On-premises for Topre

Project: TOPRE (THAILAND) CO., LTD.
Status: In Progress
Start date: 01 Feb 2025
Due date: 01 Feb 2025
Assignee: Anek Sanohkham
Priority: Normal
6

2

3

4

5

6

7

8

7

9

10

THAI INABA FOODS COMPANY LIMITED - Parent project #908: [PJ250007] Warehouse Manage... Parent project #908: [PJ250007] Warehouse Management System

Project: THAI INABA FOODS COMPANY LIMITED
Status: In Progress
Start date: 10 Feb 2025
Due date: 08 Nov 2025
Assignee: Kittisak Isarapongporn
Priority: Normal

11

12

13

14

15

8

16

17

18

19

20

21

22

9

23

24

25

26

27

28

NKT NIPPON KONPO (THAILAND) CO., LTD - Project progress work #1131: [Installation&On-site support] Project progress work #1131: [Installation&On-site support]

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: New
Start date: 28 Dec 2024
Due date: 28 Feb 2025
Assignee: Kittisak Isarapongporn
Priority: Normal
NKT NIPPON KONPO (THAILAND) CO., LTD - Project progress work #1129: [Internal Design] Project progress work #1129: [Internal Design]

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: New
Start date: 28 Dec 2024
Due date: 28 Feb 2025
Assignee: Kittisak Isarapongporn
Priority: Normal
NKT NIPPON KONPO (THAILAND) CO., LTD - Project progress work #1128: [Requirement definition] Project progress work #1128: [Requirement definition]

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: New
Start date: 28 Dec 2024
Due date: 28 Feb 2025
Assignee: Kittisak Isarapongporn
Priority: Normal
NKT NIPPON KONPO (THAILAND) CO., LTD - Project progress work #843: [Cording] Warehouse system ... Project progress work #843: [Cording] Warehouse system for business improvement for NKT Android

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: In Progress
Start date: 17 Jan 2025
Due date: 28 Feb 2025
Assignee: Taweesak Prumvised
Priority: High
NKT NIPPON KONPO (THAILAND) CO., LTD - Project progress work #828: [Cording] Warehouse system ... Project progress work #828: [Cording] Warehouse system for business improvement for NKT PHP

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: In Progress
Start date: 28 Dec 2024
Due date: 28 Feb 2025
Assignee: Ronnagon Kongsuwan
Priority: Normal

1

FUJI NAME (THAILAND) CO.,LTD - Project progress work #1056: [Installation&On-site support] Project progress work #1056: [Installation&On-site support]

Project: FUJI NAME (THAILAND) CO.,LTD
Status: New
Start date: 01 Mar 2025
Due date: 30 Jul 2025
Assignee: Anek Sanohkham
Priority: Normal
FUJI NAME (THAILAND) CO.,LTD - Project progress work #1055: [Coding] Project progress work #1055: [Coding]

Project: FUJI NAME (THAILAND) CO.,LTD
Status: New
Start date: 01 Mar 2025
Due date: 30 Jul 2025
Assignee: Anek Sanohkham
Priority: Normal
FUJI NAME (THAILAND) CO.,LTD - Project progress work #1054: [Internal Design] Project progress work #1054: [Internal Design]

Project: FUJI NAME (THAILAND) CO.,LTD
Status: New
Start date: 01 Mar 2025
Due date: 30 Jul 2025
Assignee: Anek Sanohkham
Priority: Normal
FUJI NAME (THAILAND) CO.,LTD - Project progress work #1053: [Requirement definition] Project progress work #1053: [Requirement definition]

Project: FUJI NAME (THAILAND) CO.,LTD
Status: New
Start date: 01 Mar 2025
Due date: 30 Jul 2025
Assignee: Anek Sanohkham
Priority: Normal
FUJI NAME (THAILAND) CO.,LTD - Parent project #1052: [PJ250018] ConMas i-Reporte... Parent project #1052: [PJ250018] ConMas i-Reporter 100 users On-premises for Fuji Name

Project: FUJI NAME (THAILAND) CO.,LTD
Status: In Progress
Start date: 01 Mar 2025
Due date: 30 Jul 2025
Assignee: Anek Sanohkham
Priority: Normal