18 Aug 2025

17:31 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Migration sdk from kyence to device customer. Taweesak Prumvised
09:55 Toyota Boshoku Filtration System (Thailand) Co.,Ltd 3.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
Add boxno of fg inbound schedule page. Taweesak Prumvised

14 Aug 2025

20:55 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1015 (New): [Cording] Warehouse management system PHP)
Develop inbound PO Nattaporn Chaiya
20:52 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1015 (New): [Cording] Warehouse management system PHP)
On site setup Nattaporn Chaiya
19:05 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #843 (In Progress): [Cording] Warehouse system for business improvement for NKT Android)
Fixed issues of picking function. Taweesak Prumvised
08:15 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
On site setup network. Taweesak Prumvised

13 Aug 2025

01:20 NTPT Company Limited. 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
Kittisak Isarapongporn
01:11 NTPT Company Limited. 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
Kittisak Isarapongporn
01:20 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #996 (Closed): [Development] Handheld and label print software development )
Kittisak Isarapongporn
01:13 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #996 (Closed): [Development] Handheld and label print software development )
Kittisak Isarapongporn
01:07 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #996 (Closed): [Development] Handheld and label print software development )
Kittisak Isarapongporn
01:19 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
01:09 THAI MATTO NS CO.,LTD. 4.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
01:08 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
01:05 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
01:04 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
01:03 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
01:18 A.N.I. LOGISTICS, LTD. 4.00 hours (Parent project #1057 (Closed): [PJ240041] CKD system Phase 04 & 05)
Kittisak Isarapongporn
01:14 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
01:12 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
01:02 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
01:10 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 4.00 hours (Project progress work #692 (Closed): Design and get requirements)
Kittisak Isarapongporn
01:05 NIPPN (Thailand) Co.,Ltd. 8.00 hours (Project progress work #902 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn

12 Aug 2025

23:47 NTPT Company Limited. 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
Kittisak Isarapongporn
23:17 NTPT Company Limited. 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
Kittisak Isarapongporn
23:46 Asian Stanley. International Limited 2.00 hours (Project progress work #647 (Closed): [Coding]ASI - Process Control System Phase2 -C# Windows app)
Kittisak Isarapongporn
23:41 A.N.I. LOGISTICS, LTD. 2.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:38 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:36 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:35 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:33 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:26 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:23 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:21 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:19 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:11 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:08 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #867 (Closed): [Documentation] IKD - Get requirements of project)
Kittisak Isarapongporn
23:41 NIPPN (Thailand) Co.,Ltd. 4.00 hours (Project progress work #902 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:31 NIPPN (Thailand) Co.,Ltd. 8.00 hours (Project progress work #902 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:22 NIPPN (Thailand) Co.,Ltd. 4.00 hours (Project progress work #902 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:16 NIPPN (Thailand) Co.,Ltd. 4.00 hours (Project progress work #902 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:04 NIPPN (Thailand) Co.,Ltd. 4.00 hours (Project progress work #902 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:40 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 4.00 hours (Project progress work #692 (Closed): Design and get requirements)
Kittisak Isarapongporn
23:32 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #692 (Closed): Design and get requirements)
Kittisak Isarapongporn
23:30 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #692 (Closed): Design and get requirements)
Kittisak Isarapongporn
23:22 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 4.00 hours (Project progress work #692 (Closed): Design and get requirements)
Kittisak Isarapongporn
23:14 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 8.00 hours (Project progress work #692 (Closed): Design and get requirements)
Kittisak Isarapongporn
23:39 THAI MATTO NS CO.,LTD. 4.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:37 THAI MATTO NS CO.,LTD. 4.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:34 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:29 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:25 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:21 THAI MATTO NS CO.,LTD. 4.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:20 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:11 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:07 THAI MATTO NS CO.,LTD. 4.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:00 THAI MATTO NS CO.,LTD. 8.00 hours (Project progress work #873 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:24 A.N.I. LOGISTICS, LTD. 4.00 hours (Parent project #712 (Closed): EKD System phase4 for ANI Ayuthaya)
Kittisak Isarapongporn
23:14 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #996 (Closed): [Development] Handheld and label print software development )
Kittisak Isarapongporn
23:10 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #996 (Closed): [Development] Handheld and label print software development )
Kittisak Isarapongporn
23:05 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #996 (Closed): [Development] Handheld and label print software development )
Kittisak Isarapongporn

11 Aug 2025

17:33 Prospira Thailand Co., Ltd. 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-Fix and New Requirement Priroj Neamjarn
17:32 Prospira Thailand Co., Ltd. 8.00 hours (Project progress work #1010 (Closed): Warehouse management system )
-Fix and New Requirement Priroj Neamjarn
17:26 THAI INABA FOODS COMPANY LIMITED 7.00 hours (Project progress work #1015 (New): [Cording] Warehouse management system PHP)
Develop Inbound SEMI Page Nattaporn Chaiya
17:25 THAI INABA FOODS COMPANY LIMITED 1.00 hour (Project progress work #1015 (New): [Cording] Warehouse management system PHP)
Meeting Internal with team Nattaporn Chaiya
16:51 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Migration sdk from kyence to device customer. Taweesak Prumvised

10 Aug 2025

21:01 SHINSEI KOKI (THAILAND) CORPORATION LIMITED. 48.00 hours (Problem-Bug #1021 (Closed): issue onsite 29 July 2025)
Yutthapong Sricha
 