Activity
From 08 Jul 2025 to 17 Jul 2025
17 Jul 2025
- 17:29 YAMATO ELECTRIC (THAILAND) CO., LTD. Project progress work #1000 (Confirmation request): [Change requirement] Meeting Change requirement of HT
- 17:28 THAI METALTECH CO., LTD. Project progress work #500 (In Progress): [Coding] Warehouse management system handyterminal Java Phase02
- 16:15 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-Training user WIP inbound, FG inbound
tomorrow
-Fix new Request
-Stock Count
16 Jul 2025
- 17:33 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-Simp Outbound
tomorrow
-Training user WIP inbound, FG inbound
-Stock Count
15 Jul 2025
- 17:07 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-RM Return
tomorrow
-Simp Outbound
-Stock Count
14 Jul 2025
- 17:20 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-DL Transfer
tomorrow
-Simp Outbound
-RM Return
-Stock Count
11 Jul 2025
- 17:45 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-fix issue SIMP Inbound
-Stock Check
-Change Location
tomorrow
-Transfer
-DL transfer
-Stock Count
09 Jul 2025
- 16:32 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-fix issue RM-inbound, MO Request outbound
-Make manual RM-inbound, MO Request outbound
tomorrow
-Transfer
...
08 Jul 2025
- 17:12 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-Stock
tomorrow
-Transfer
-DL transfer
-Stock - 10:59 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #1017 (Closed): Project Management for Task Review
- Task review for the backend and dashboard.
- 10:52 SIAM NITORI Co., Ltd. Project progress work #1016 (New): Asprova Phase 2 Implementation
- Configure Asprova data based on the provided data from Siam Nitori.
Also available in: Atom