Activity
From 04 Jul 2025 to 13 Jul 2025
11 Jul 2025
- 17:45 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-fix issue SIMP Inbound
-Stock Check
-Change Location
tomorrow
-Transfer
-DL transfer
-Stock Count
09 Jul 2025
- 16:32 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-fix issue RM-inbound, MO Request outbound
-Make manual RM-inbound, MO Request outbound
tomorrow
-Transfer
...
08 Jul 2025
- 17:12 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-Stock
tomorrow
-Transfer
-DL transfer
-Stock - 10:59 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #1017 (Closed): Project Management for Task Review
- Task review for the backend and dashboard.
- 10:52 SIAM NITORI Co., Ltd. Project progress work #1016 (New): Asprova Phase 2 Implementation
- Configure Asprova data based on the provided data from Siam Nitori.
07 Jul 2025
- 17:10 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-Fix issue Inbound Process (First training)
-MO Outbound Process
-SO Outbound Process
tomorrow
-Transfer
...
04 Jul 2025
- 17:09 PROSPIRA THAILAND CO., LTD. Project progress work #1010: Warehouse management system
- today
-Fix issue Inbound Process (First training)
-MO Outbound Process
-SO Outbound Process
tomorrow
-MO Outboun...
Also available in: Atom