Activity
From 05 Apr 2025 to 14 Apr 2025
12 Apr 2025
- 04:01 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Completed user manual for the project.
- 04:01 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Created the user manual for the project.
11 Apr 2025
- 17:06 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- -Adjust back-end input dummy check sheet
- 16:50 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Develop Monitor Mode
- 16:28 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #995 (Closed): get requirement and create specification Doc. [Calling maintenance staff system])
- meeting with customer, update all project , modify spec and operation flow
- 16:24 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #995 (Closed): get requirement and create specification Doc. [Calling maintenance staff system])
- create specification Doc. R1 : operation, flow chart, document infomation
- 16:23 ASIAN STANLEY. INTERNATIONAL LIMITED. 2.00 hours (Project progress work #995 (Closed): get requirement and create specification Doc. [Calling maintenance staff system])
- create specification Doc. R1 : config, operation, flow chart
- 16:27 ASIAN STANLEY. INTERNATIONAL LIMITED. 2.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- Verify the accuracy of the report
- 16:19 ASIAN STANLEY. INTERNATIONAL LIMITED. 1.00 hour (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- support user online: update plan, query report for customer,
- 16:19 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- Verify the accuracy of the report with K.fight, support user online:query report for customer,
- 16:19 ASIAN STANLEY. INTERNATIONAL LIMITED. 1.00 hour (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- support user online: update plan, query report for customer,
- 16:26 ASIAN STANLEY. INTERNATIONAL LIMITED. 6.00 hours (Project progress work #788 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing classify rank system])
- meeting with customer and modify spec
- 16:16 YAMATO ELECTRIC (THAILAND) CO., LTD. 3.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- support user online
- 16:16 YAMATO ELECTRIC (THAILAND) CO., LTD. 5.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- support user online about operation system, check schedule , bom, unit, label
10 Apr 2025
- 17:23 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust back-end input dummy check sheet
- 17:03 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Fix Meter Compare and update on production
- 17:03 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Develop Chiller, Develop Air Flow
- 17:02 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Develop Data Export Fix Export Excel
- 17:01 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Develop Meter Detail
09 Apr 2025
- 17:49 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- Fixed issues after trial demo on site.
- 17:48 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- On site trial test delivery function.
- 17:16 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Created the user manual for the project.
- 17:14 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Fixed all identified bugs and completed the testing process for the entire project.
- 17:13 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Performed full testing across all pages and functions in the project to identify bugs and inconsistencies.
- 17:08 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Developed and completed Page Tracking System.
- 17:07 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Developed Page Tracking System Backend.
- 17:07 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Developed Page Tracking System Fontend.
- 17:05 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Developed and completed Loading Report web Page Transport.
- 17:03 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Developed Loading Report function show picture delivery tracking web Page Transport.
- 16:51 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- -Adjust back-end input dummy check sheet
- 16:51 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- -Adjust back-end input dummy check sheet
- 16:51 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- -Adjust back-end input dummy check sheet
07 Apr 2025
- 17:18 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust font-end/back-end Dummy check sheet
- 17:17 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust font-end/back-end input dummy check sheet
- 17:17 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- Fixed issues after trial demo on site.