- 17:18 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust font-end/back-end Dummy check sheet
- 17:17 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust font-end/back-end input dummy check sheet
- 17:17 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- Fixed issues after trial demo on site.
04 Apr 2025
- 18:02 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Develop Meter Detail and Update function Data Export on Customer Production
- 16:36 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust font-end input dummy check sheet
- 16:36 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust font-end input dummy check sheet
- 12:07 ASIAN STANLEY. INTERNATIONAL LIMITED. 5.00 hours (Project progress work #788 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing classify rank system])
- Meeting with customer, modify spec,
- 12:05 YAMATO ELECTRIC (THAILAND) CO., LTD. 3.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- modify manual and support user online
- 11:56 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- support uer on site [stock inventory]
- 11:54 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- update system & trainning & support onsite
- 12:00 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #509 (In Progress): Soraya Norasing Taking Day off January-December 2024)
- take sick leave today because I have migraine.
- 11:59 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- test report with K.fight and Verify the accuracy of all 4 menu reports.
- 11:58 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- Metting with K.Kam about dashboard, meeting with K.fight about report and test
- 11:57 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- meeting with customer on site about dashboard, print rank classify
- 11:53 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- meeting, modify, add QC function, re-print function, and test with K.nueng
- 11:53 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- meeting, modify, add QC function, re-print function
- 11:52 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
- meeting, modify, add QC function
- 11:51 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
- meeting with K.fight test report & master , support usert add printer
03 Apr 2025
- 17:00 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Develop Meter Compare
- 09:33 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Develop Meter Compare
- 16:54 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust site,Adjust site map -Adjust main screen input check list
- 16:54 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust site,Adjust site map -Adjust main screen input check list
02 Apr 2025
- 16:37 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust site map
- 16:36 DENSO INNOVATIVE MANUFACTURING SOLUTION ASIA CO., LTD 8.00 hours (Project progress work #913 (Closed): [Coding] Web app Daily check project C#, HTML, CSS and JS)
- Adjust site map
- 16:30 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- Create i-Reporter form
01 Apr 2025
- 17:13 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #910 (Closed): Back-End Web dashboard application PHP)
- Develop Meter Compare
- 17:12 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Fix bug q-gate
- 15:05 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- Support i-Reporter
- 15:03 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (31/03) Manual i-Reporter for Sumitomo
- 15:02 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (29/03) Manual i-Reporter for Sumitomo
- 15:02 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (28/03) Manual i-Reporter for Sumitomo, Meeting online with NMT, An earthquake occurred at 1:20 p.m.
- 15:00 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (27/03) Outside Fuji name(Kick-off), Manual i-Reporter for Sumitomo
- 14:59 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (26/03) Manual i-Reporter for Sumitomo
- 14:58 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (25/03) Outside NTN (Rayong)
- 14:56 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- (24/03) Training with sale Nichiden, Papasu customer on-site about I-reporter
- 13:42 MITSUI PRECISION THAI CO., LTD. 2.00 hours (Project progress work #912 (Closed): [Documentation] Get requirements of project)
- Meeting at on-site
- 12:16 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Developed Loading Report function edit confirm web Page Transport.
- 12:13 NKT NIPPON KONPO (THAILAND) CO., LTD 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
- Developed Loading Report web Page Transport.
- 12:05 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- The newly developed function for the production process, including material usage and quality control (QC), has been ...
- 12:04 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- The function for the production process, including material usage and quality control (QC), has been developed and co...
- 12:02 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- A new requirement has been added to develop a function for the production process, including material usage and quali...
- 11:57 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- I'm supporting users on site for the month-end stock inventory update.
- 12:00 THAI METALTECH CO., LTD. 8.00 hours (Project progress work #605 (Closed): [Coding] Warehouse management system Web app PHP Phase02)
- Meeting testing with user developed and completed fix bug inbound material po handdy and web.
31 Mar 2025
- 20:16 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Adjust Outbound Report
- 08:12 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Install system at NKI
- 08:12 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Install system at NKI
- 08:11 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Install system at NKI
- 08:11 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Install system at NKI
- 08:11 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Install system at NKI
- 17:27 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Fix Bug Vanning and Add function keep log approve sc flag
- 17:27 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Fix Bug Vanning and Add function keep log approve sc flag