22 Mar 2025

07:57 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
Installation at NKI Priroj Neamjarn
07:57 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
Installation at NKI Priroj Neamjarn
07:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
Installation at NKI Priroj Neamjarn
07:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
Installation at NKI Priroj Neamjarn
07:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
Installation at NKI Priroj Neamjarn
07:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
Installation at NKI Priroj Neamjarn
07:55 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
Installation at NKI Priroj Neamjarn
07:55 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
Installation at NKI Priroj Neamjarn

21 Mar 2025

18:02 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #899 (Closed): MOC Monitoring system)
Fixed web socket installation on site. Taweesak Prumvised
12:13 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #899 (Closed): MOC Monitoring system)
Fixed web socket installation on site. Taweesak Prumvised
17:03 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
Support Fix bug, install Nattaporn Chaiya
16:30 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
Support i-Reporter Panthita Roekdee
10:33 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
Support user onsite (install function edit schedule plan production,material, training user injection. Ronnagon Kongsuwan
 