Activity
From 20 Mar 2025 to 29 Mar 2025
22 Mar 2025
- 07:57 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Installation at NKI
- 07:57 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Installation at NKI
- 07:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Installation at NKI
- 07:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Installation at NKI
- 07:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Installation at NKI
- 07:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Installation at NKI
- 07:55 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Installation at NKI
- 07:55 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Installation at NKI
21 Mar 2025
- 18:02 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #899 (Closed): MOC Monitoring system)
- Fixed web socket installation on site.
- 12:13 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #899 (Closed): MOC Monitoring system)
- Fixed web socket installation on site.
- 17:03 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Support Fix bug, install
- 16:30 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- Support i-Reporter
- 10:33 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #594 (Closed): [Coding] Warehouse management system handyterminal PHP web)
- Support user onsite (install function edit schedule plan production,material, training user injection.
20 Mar 2025
- 17:28 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #845 (Closed): [Cording] Warehouse management system for NKI PHP)
- Fix issues
- 16:49 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #891 (New): For internal meeting and other)
- Support i-Reporter
- 11:35 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
- test and fix bug in api (step taping check)
- 11:26 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
- add printer to server , setup printer, support user online
- 11:18 ASIAN STANLEY. INTERNATIONAL LIMITED. 3.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
- test windows app with K.fight
- 10:47 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
- Install update & support user on site
- 11:33 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- test and fix bug (bonding check process can't scan machine)
- 11:27 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- meeting at NTPT about asprova
- 11:24 ASIAN STANLEY. INTERNATIONAL LIMITED. 1.00 hour (Project progress work #788 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing classify rank system])
- meeting online get requirement with customer
- 11:19 ASIAN STANLEY. INTERNATIONAL LIMITED. 5.00 hours (Project progress work #788 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing classify rank system])
- prepare spec doc
- 11:23 ASIAN STANLEY. INTERNATIONAL LIMITED. 3.00 hours (Project progress work #790 (Closed): [Colding] Handy terminal BT-A500 Java application [Calling maintenance staff system])
- meeting with customer get requirement
- 11:20 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- support user onsite
- 11:20 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #797 (Closed): [Installation] HT_YDT WMS)
- support user onsite
- 08:19 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 8.00 hours (Project progress work #505 (Closed): [Coding] Warehouse management system handyterminal Java)
- Trial demo and fixed some issues #2.
Also available in: Atom