24 Jan 2025

17:36 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #829: [Colding] C# linkage application of AS400
today
-adjust linkage data windows application
process FCT82T
process FCT83T
tomorrow
-adjust linkage data windo...
Priroj Neamjarn

23 Jan 2025

17:33 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #829: [Colding] C# linkage application of AS400
today
-adjust linkage data windows application
process FCT82T
tomorrow
-adjust linkage data windows application...
Priroj Neamjarn

22 Jan 2025

18:41 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
-today
internal test
Fix bug
Priroj Neamjarn

21 Jan 2025

19:41 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
today
-Transfer in process
tomorrow
-Internal test
Priroj Neamjarn

20 Jan 2025

18:56 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Update Setup/Vanning Process
-Update QGate Process
Priroj Neamjarn

19 Jan 2025

08:50 A.N.I. LOGISTICS, LTD. Project progress work #892 (Closed): [Development] Enhance the web function and ui
Kittisak Isarapongporn

18 Jan 2025

16:44 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Adjust Setup/Vanning Process
Priroj Neamjarn

17 Jan 2025

18:54 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-install the application.
Priroj Neamjarn
16:10 TOMAS TECH CO., LTD. Project progress work #891: For internal meeting and other
(17/01)Prepare for i-Reporter training(Sumitomo Rubber) Panthita Roekdee
10:31 YAMATO ELECTRIC (THAILAND) CO., LTD. Project progress work #797: [Installation] HT_YDT WMS
test & onsite support Soraya Norasing

16 Jan 2025

16:47 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
today
-NG Manual
-Transfer in process
tomorrow
-NG Manual
-Transfer in process
Priroj Neamjarn
16:44 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-install the application.
Priroj Neamjarn

15 Jan 2025

17:08 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
today
-NG Manual
-Transfer in process
tomorrow
-NG Manual
-Transfer in process
Priroj Neamjarn
16:50 TOMAS TECH CO., LTD. Project progress work #891: For internal meeting and other
(15/01)Prepare for i-Reporter training(Sumitomo Rubber), Create form i-Reporter demo(Musashi) Panthita Roekdee
16:46 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-install the application.
Priroj Neamjarn
 