21 Jan 2025
- 19:41 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
- today
-Transfer in process
tomorrow
-Internal test
20 Jan 2025
- 18:56 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Update Setup/Vanning Process
-Update QGate Process
19 Jan 2025
- 08:50 A.N.I. LOGISTICS, LTD. Project progress work #892 (Closed): [Development] Enhance the web function and ui
18 Jan 2025
- 16:44 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Adjust Setup/Vanning Process
17 Jan 2025
- 18:54 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application. - 16:10 TOMAS TECH CO., LTD. Project progress work #891: For internal meeting and other
- (17/01)Prepare for i-Reporter training(Sumitomo Rubber)
- 10:31 YAMATO ELECTRIC (THAILAND) CO., LTD. Project progress work #797: [Installation] HT_YDT WMS
- test & onsite support
16 Jan 2025
- 16:47 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
- today
-NG Manual
-Transfer in process
tomorrow
-NG Manual
-Transfer in process - 16:44 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application.
15 Jan 2025
- 17:08 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
- today
-NG Manual
-Transfer in process
tomorrow
-NG Manual
-Transfer in process - 16:50 TOMAS TECH CO., LTD. Project progress work #891: For internal meeting and other
- (15/01)Prepare for i-Reporter training(Sumitomo Rubber), Create form i-Reporter demo(Musashi)
- 16:46 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application.
14 Jan 2025
- 16:38 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application. - 09:40 TOMAS TECH CO., LTD. Project progress work #891 (New): For internal meeting and other
- For internal meeting, Create i-Reporter form demo, Meet customers, Training i-Reporter, Support i-Reporter and other.
- 09:31 TOMAS TECH CO., LTD. Project progress work #714: For internal meeting and other
- (14/01)Training i-reporter plan (Sumitomo)
13 Jan 2025
- 17:08 IRODORI SHISEI (THAILAND) CO., LTD. Project progress work #890 (In Progress): ME Assembly [ Aluminum Frame ]
- 16:57 IRODORI SHISEI (THAILAND) CO., LTD. Project progress work #890 (Closed): ME Assembly [ Aluminum Frame ]
- - Assembly Aluminum Frame at BTT
- 2D/3D Drawing
- Collect items (keyence)
- Site survey - 16:59 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application. - 16:50 TOMAS TECH CO., LTD. Sales support #861 (Confirmation request): Daikin Compressor
- 16:49 TOMAS TECH CO., LTD. Project progress work #670 (Confirmation request): Demo LEGO
- 16:48 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #841 (Confirmation request): Table installation
- 16:47 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #837 (Confirmation request): ME Assembly [ Table ]
- 16:45 TOMAS TECH CO., LTD. Sales support #710 (Confirmation request): Demo Keyence 4 Set